5.17
Precabling
Step 63
Now it is recommend ed to start with the cabling.
Guid ing the cables is easier without the core
elements (illumination unit, projection unit) installed.
The systems have been designed with two different
cable lines, one for the power cables and one for the
data and LAN cables.
Therefore there are two parallel cable fixation
facilities on the sidewalls and on the cable hub.
Step 64
The schematic at the left shows the layout of the
cabling. Guide the cables accordingly.
At the bottom of a column, all cables are fixed to the
cable hub and guided to the right.
Position the cables.
Fix the cables only loosely – finalizing the cabling and
fixing will be done after the installation of the
illumination unit and the projection unit, see Step 70.