Installation instruction
RWA - Control Unit EMB 7300

i

nDiCator

 

anD

 C

ontrol

 e

lements

 / m

aintenanCe

LED display for breakglass unit (HSE)

Display

State

Normal operation

EMERGENCY-OPEN / alarm 
(mains operation)

EMERGENCY-OPEN / alarm 
(back-up accumulators mode) 

power failure (highest priority)

Fault to breakglass unit lines

Fault to smoke detector lines

Fault in motor-line 1

Fault in motor-line 2

Fault at EMERGENCY-CLOSE button

Back-up accumulators fault
(lowest priority)

Maintenance expired

Rain active

Wind active

Wind and rain active

The functionalities of the 
external LED outputs are 
configurable.

A

S

B

EMERGENCY-OPEN 
LED display

Fault

off

off

flashes

flashes

on

on

blinks slowly

blinks slowly

blinks slowly

blinks quickly

2x blinking

off

off

on

off

on

on

off

off

off

off

off

off

off

off

on

on

on

Operation

!

*

 

depending on the configuration „EMERGENCY- 

    OPEN Troubleshooting“OPEN or CLOSE 

A

S

B

A

off

on

on

off

off *

off *

off *

off *

off

off

off

off

off

off

*

 

depending on the configuration „EMERGENCY- 

    OPEN Troubleshooting“OPEN or CLOSE 

*

 

depending on the configuration „EMERGENCY- 

    OPEN Troubleshooting“OPEN or CLOSE 

*

 

depending on the configuration „EMERGENCY- 

    OPEN Troubleshooting“OPEN or CLOSE 

!

M

AintEnAnCE

 

And

 M

odifiCAtion

To ensure continuous function and safety of the complete system periodic 
maintenance by a specialist company is required at least once a year 
(as mandated by law for smoke and heat exhaust systems). Operational 
readiness must be checked regularly, at least once a month.

The information provided in these instructions for the maintenance must 
be observed. Malfunctions must be remedied immediately. Only spare 
parts made by the manufacturer may be used. Between maintenan-
ce intervals the operator shall carry out or order a visual inspection at 
least once and document it in writing in the log book. We recommend 
a maintenance contract with a specialist company authorized by the 
manufacturer. A sample maintenance contract can be downloaded from 
the homepage of 

F

Irm

 A

umüller

 A

umAtIc

 G

mb

H

 

(

www.aumueller-gmbh.de

).

After opening of the system housing voltage carrying 
parts are exposed! Each time, before performing main-
tenance work or making a modification of the structure 
(e.g. replacement of the window drive), the mains voltage 
and – as far as available – the accumulators must be com-
pletely discunnected and secured against unintentional 
reactivation (lock in separation mode).

What has to be serviced?

•  Check all 

connections

 (also the ones in the Control Unit) for tight- 

  ness and for possible damage.
•  Check all 

fuse links

.

•  Check charge level and installation date of back-up 

accumulators 

 

and exchange the accumulators, if necessary (accumulators must 

  be exchanged 4 years after installation). Note down the 
  exchange date on the accumulator. Dispose of removed accumulators 
  in conformity with legal requirements.
•  Check 

drive control

 for proper function. Also check drive run 

  directions. If the actuation is correct but the drive is still not 
   working properly, pay regard to the assembly and maintenance 
  instructions of the drive manufacturer.

•  Check all 

breakglass units

 and ventilation buttons for functionality 

  (do the drives move in the direction indicated on the buttons?)
•  Check all 

smoke detectors

 according to manufacturer’s instructions  

  using test gas.
•  Remove dirty or faulty 

detectors

 and send them to the manufacturer  

  for repair or cleaning.
•  When connecting 

wind and rain sensors

 check for proper functionality 

  of the sensors, readjust the wind response threshold, if necessary.
•  Check the 

configuration

 with our system software and test if the 

  system works with the stored configuration.
The service instructions for the connected components are decisive 
for their maintenance.

07

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

A

S

B

A

Содержание EMB 7300

Страница 1: ...g to EN12101 10 and control panel according to prEN12101 9 RWA Control Unit EMB 7300 2 5 A 5 A 10 A 20 A tested electrical control device EMB 7300 with recognition number G 514001 Installation and Commissioning Instructions ...

Страница 2: ...Maximal detector in drive line Installation step 3 Connection of automatic and manual smoke detectors Installation step 4 Connecting wind and rain sensors Installation step 5 Installing relay plug in card REL and BUS connection Installation step 6 Connecting power supply Installation step 7 System configuration using software EMB Kompakt Installation step 8 Enabling operation completing installati...

Страница 3: ... V Volts PU Packaging Units Vpp Residual ripple Voltage Peak Peak W Watts Ω k Ω Ohm Kilohms Figures AC Alternating current 50Hz 60Hz DC Direct current I Electric current L Length ME Module space unit 1 ME 23 mm NC Contact closed normally closed NO Contact opened normally opened P Electric power R Electrical resistance U Electric voltage Um Change over switch Colour abbreviation according to IEC 60...

Страница 4: ... lives and protect property Furthermore the electric window ensures fresh air supplied for natural ventilation of the building Intended use according to the Declaration of Con formity The control device is intended for stationary installation and electrical connection as part of a building In accordance with the attached Declaration of Con formity the control device in combination with electromoti...

Страница 5: ...e each intervention in the Control Unit of the system Clamping points must be checked for tightness of threa ded connections and cable ends Access to junction boxes clamping points and external drive control systems must be ensured for maintenance work Commissioning operation and maintenance After the installation and after each modification in the set up all functions must be checked with a trial...

Страница 6: ...issue of a Declaration of Conformity according to European guidelines The prerequisites of the system see chapter Systems confi guration of software must be checked prior to installation The Software clause for handing over the standard soft ware as part of shipments of the ZVEI German Electrical and Electronic Manufacturer s Association is accepted as legally binding upon installation See our hom...

Страница 7: ...ance free back up accumulators 2x 12 V 2 3 Ah Part No 541000 Application Compact Control Unit for smoke and heat exhaust ventilation systems operating with 24V DC voltage suitable for staircases TECHNICAL DATA Rated values Operating voltage 230V AC 195 253 V AC 50 60 Hz Max power consumption 460 W Output voltage 24V DC 20 28 V DC 0 5 Vpp Output current 5 0 A Ambient temperature range 5 C 40 C Prot...

Страница 8: ...ting steel sheet RAL 7035 light grey Dimensions WxHxD 400 x 300 x 150 mm Connection terminals 1 5 mm Drives 6 mm rigid wire Motherboard 1 RWA group 2 Vent groups Application Compact Control Unit for smoke and heat exhaust ventilation systems operating with 24V DC voltage suitable for staircases TECHNICAL DATA Rated values Operating voltage 230V AC 195 253 V AC 50 60 Hz Max power consumption 805 W ...

Страница 9: ...5 x 285 x 122 mm Version 2 5A 5A 400 x 300 x 150 mm Version 10A 400 x 400 x 200 mm Version 20A Preparing assembly Technical Data Warning Important instructions for safe assembly Fully observe all instructions incorrect assembly may lead to serious injuries Before starting the installation please check with the delivery note that the delivery is complete and correct any complaints received later ca...

Страница 10: ... exhausting natural ventilation Input for ventilation line 1 max 10 vent buttons Output for drive line 2 only for EMB 7300 5 A 0102 10 A 0102 20 A 0102 Input for ventilation line 2 max 10 vent buttons only for MB 7300 5 A 0102 10 A 0102 20 A 0102 Housing of Control Unit with or without integrated break glass unit and ventilation button Connections for wind and rain sensor disabled in case of alarm...

Страница 11: ...ine length and cross section A drives depend on the type of drive and on the number of drives Line length and cross section can be determined according to the following formula Formula to calculate the required wire cross section of a infeed line A cross section of line in mm2 L line length in m I current of connected drives in A U line voltage drop 2 V DC total length infeed line voltage drop Bef...

Страница 12: ... 5 A nominal current EMB 7300 10 A max 10 A nominal current EMB 7300 20 A 2x max 10 A nominal current RWA release in case of fire overrides ventilation No ventilation in the event of a mains power supply failure accumulator operation RWA release in case of fire overrides ventilation No ventilation in the event of a mains power supply failure accumulator operation Automatic ventilation control e g ...

Страница 13: ...ance with applicab le legal requirements The terminal cross section for the drive connection is EMB 7300 0101 max 2 5 mm flexible EMB 7300 0101 T max 4 0 mm rigid wire EMB 7300 0101 max 4 0 mm flexible EMB 7300 0101 T or EMB 7300 0102 max 6 0 mm rigid wire EMB 7300 0101 EMB 7300 0102 EMB 7300 0102 2 5A 2 5A 5A 5A 5A 10A 10A 20A Formula to calculate the required wire cross section of a infeed line ...

Страница 14: ...nection of automatic and manual smoke detectors 04 OK 11 10 9 8 7 6 5 4 3 2 1 1 1 1 22 5 71 1 13 14 15 16 17 18 19 A S B 1 72 OK 11 10 9 8 7 6 5 4 3 2 1 10 k IN C O M O UT IN C O M O UT IN C O M OU T BMA 1 2 3 4 5 1 22 1 22 COM OUT IN IN IN OUT OUT COM COM RE 1 13 14 15 16 18 19 1 2 3 4 5 6 7 8 9 10 11 2 5 A 5 A 20 A 10 A Automatic smoke detector Breakglass unit Buttons Indicators COM Indicators m...

Страница 15: ... rain sensors is deactivated Before mounting and positioning the wind rain sen sors carefully read the safety and assembly instructions provided with the products They are part of the system documentation and must be adhered to and kept accor dingly e g for servicing purposes Installation step 4 Connecting wind and rain sensors 2 5 A 5 A 20 A 10 A Installation step 4 Connecting Wind and Rain Senso...

Страница 16: ... installation an connect when disconnected from the mains power supply Switch off power supply and secure against reconnection The motherboard has two slots for using one relay plug in card REL 65 each order no 650200 so that external processing of messages via floating relay contact 1 x change over switch 42 V max 0 5 A is possible Cable installation must be in compliance with applicable legalreq...

Страница 17: ... AC 50 60 Hz On the version with front mounted push button the connector may be removed Routing via external fuse and switching component PE BU BU BU 2 x back up accumulator 2 3 Ah 12V Ensure correct polarity when connecting red blue Attachment of the accumulators with the optional accumulator holder set Part No 683250 only for compact housing The accumulator set may also be fastened to the housin...

Страница 18: ... A N N 1 72 N L V VGG N L USB Do not remove cover F1 F2 F3 Switching power supply 5A RD RD RD RD RD L L Cover SMOKE VENT N N 225 mm 400 mm 285 mm 300 mm 10 A oder 400 mm 20 A Wiring duct 230V AC 50 60 Hz 230V AC 50 60 Hz Version 0102 only Routing via external fuse and switching component Routing via external fuse and switching component PE PE BU BU BU BU Output DC 24V Switching power supply 10 A o...

Страница 19: ...free version of the system software version VIEW can be downloaded from the homepage www aumueller gmbh de The software can be installed on a computer notebook or net book Please pay regard to the hardware and system requirements see below Follow the instructionsdisplayed on the screen to install the program The software offers many features to adapt the system to your requirements However you sho...

Страница 20: ...s RWA systems require a logbook in which all important master data have to be entered prior to operation enable and all operational events during the period in operation The logbook is part of the system documents and must be stored and available to authorized staff at all times We advise to perform an insulation measurement of the cable network before enabling operation of the plant and to keep a...

Страница 21: ...ght open circuit or short circuit in manual fire alarm faulty power monitoring Indicator S blinks slowly open circuit or short circuit in smoke detector line faulty power monitoring Indicator S blinks 2 times service required indicator B green lights up Indicator S blinks 3 times fault bus module e g radio module Indicator S blinks 4 times open circuit or short circuit in drive line 1 faulty power...

Страница 22: ... 1 7 2 USB 1 REL65 2 REL65 BUS Module BUS Wind Rain RM HSE LT 2 F1 A A N N Drive 1 Stecker für Front Button Drive 2 A Z Reset LT 1 Indicators GN Operation YE Fault RD Alarm EMERGENCY OPEN Drive run direction and position A OPEN RD Z CLOSE GN Drive run direction A OPEN RD Z CLOSE GN Duo LED 2 x on version 0102 The Duo LED displays the current switched direction of the line vol tage for the duration...

Страница 23: ... contract with a specialist company authorized by the manufacturer A sample maintenance contract can be downloaded from the homepage of Firm Aumüller Aumatic GmbH www aumueller gmbh de After opening of the system housing voltage carrying parts are exposed Each time before performing main tenance work or making a modification of the structure e g replacement of the window drive the mains voltage an...

Страница 24: ...wing Improper use of the product Improper installation commissioning operation maintenance or repair of the product Operating the product by defect and improper installed or not functioning safety and protection devices Ignoring instructions and installation requirements in these in structions Unauthorized constructional modifications at the product or accessories Disaster situations due to effect...

Страница 25: ...25 Installation instruction RWA Control Unit EMB 7300 08 ...

Страница 26: ... different Control Unit versions Remark Terminals Drive 1 Drive 2 only version 0102 CLOSE CLOSE CLOSE CLOSE CLOSE CLOSE ZU Operation Fault COM COM OPEN OPEN OPEN OPEN OPEN OPEN Buttons Buttons Buttons Indicators Indicators Indicators EMERGENCY EMERGENCY OPEN OPEN COM Line monitoring Line monitoring COM COM COM COM COM only version 0102 optional optional Ventilation 1 Ventilation 2 1 REL 65 2 REL 6...

Страница 27: ...rvices The publication of these assembly and commissioning instructions supersedes all previous editions The VdS approval includes the following Control Units EMB 7300 without RWA button EMB 7300 with orange RWA button EMB 7300 without RWA button EMB 7300 with orange RWA button EMB 7300 EMB 7300 2 5A 2 5A 5A 5A 10A 20A Certificate and Declaration of Conformity We declare under our sole responsibil...

Страница 28: ...en Tel 49 8271 8185 0 Fax 49 8271 8185 250 info aumueller gmbh de 9000017000_V0 1_KW05 14 www aumueller gmbh de AUMÜLLER AUMATIC GMBH Gemeindewald 11 86672 Thierhaupten Tel 49 8271 8185 0 Fax 49 8271 8185 250 info aumueller gmbh de 9000007401_V2 4_KW46 20 ...

Отзывы: