CM5000 User Manual
UM-CM5000-FW3.5.2.0-REV0.0
2019-07-08
www.ateme.com
Page 28
3. Installation
3.1. Hardware setup
Step 1: Unpack and install the CM5000
Unpack your CM5000 unit and install it.
• For Stand Alone installations, place the unit on a stable surface. It requires clearance above and on each side to
allow for cooling.
• Alternatively, for Rack installations, mount the unit in a standard 19-inch rack. The CM5000 requires 1U of vertical
space.
Note
Note for Rack installations: Carefully slide the CM5000 into a shelf space in the rack. Use your equip-
ment rack's screws to secure the device in place, in the rack.
Step 2: Connect the power
Connect the CM5000 input power [B1] to a power outlet using the provided power cord.
Step 3: Connect to Ethernet
Connect the network cables to Ethernet interfaces.
• The Stream interfaces [B3] and [B4] should be plugged into your broadcast network
• The MGT interface [B2] should be plugged into your supervision network
Note
If you do not have different networks, using the streaming port to do both broadcasting and administra-
tion is possible. This is not recommended for production phases.
Step 4: Connect SDI input
Connect the SDI input cables to [X1] (see Section 2.3, “ Rear View ”).
Step 5: Power up
Power up the CM5000, switching the 0/1 button [P1] into the position 1.