9
Amphenol Network Solutions
All rights reserved. 12.18.19 139688-3
509.926.6000 – amphenol-ns.com
100A Dual-Feed
Breaker Panel
9. While holding the breaker out from the front of the panel, grasp the
LINE
connector of the breaker
with needle-nose pliers.
10. Hold the
LINE
connector with pliers and then pull the breaker, wiggling it until the breaker is free from
the connector. Continue to hold the
LINE
connector with the pliers. Do not allow the connector to
contact the panel chassis.
11. With your free hand, pick up the new breaker and check the orientation of the new breaker.
12. Press the spade connector of the new breaker into the pliers-held
LINE
connector until it is
fully seated.
Visually inspect the connection to be sure full contact is made between the
LINE
connector and the
breaker spade connector.
13. Place the
LOAD
conductor connector on the
LOAD
spade connector of the breaker.
Visually inspect the connection.
14. Gently place breaker back into panel. Push on front of breaker until tabs are cleared and breaker is
secure in the panel.
15. If the input power was turned off, restore input power and turn on breakers one at a time.
16. When you turn the new breaker on, check the output terminal for correct polarity.