F. Position columns
(See Fig. 14)
Check the columns plumbness with level bar, and adjusting with the shims if the
columns are not vertical.
G. Fix anchor bolts
1. Prepare anchor bolts
(See Fig. 15)
.
Fig. 15
2. Using the prescribed rotary hammer drill, and drill all the anchor holes and install
the anchor bolts. Then tighten the anchor bolts
(See Fig. 16).
Note:
Torque of Anchors is 150N.m .Minimum embedment of Anchors is
3-1/2”
.
Fig. 16
Fig. 14
Lock washer
Washer
Nut
90mm
Check the columns
plumbness with level bar
from front and side
136-1/4
”
112-1/4
”
Содержание 209X
Страница 1: ...TWO POST LIFT Model BP 9X...
Страница 4: ...2 MODEL 209X SPECIFICATIONS 3 1 2 12 1 2...
Страница 5: ...3 Fig 2 For Model 209X 100 3 4 28 50 5 8 28 50 5 8...
Страница 12: ...10 H Lift the carriages up by hand and make them be locked at the same level See Fig 17 Fig 17...
Страница 14: ...12 K Install hydraulic power unit and oil hose assy See Fig 20 Fig 19 71 68 71A 71 69A 70 71 69 71...
Страница 19: ...17 Terminal 3 of control button is connected with terminals L1of AC contactor Fig 27 Single phase...
Страница 20: ...18 IV EXPLODED VIEW Model BP 9X Fig 28 Car in direction...
Страница 21: ...19 Cylinders MANUAL POWER UNIT 220V 60Hz 1Phase Fig 30 Fig 29...