Alpha InTec 40GS2 - Routine Servicing
7.2 PREPARE FOR SERVICING - Fig. 7.1
1. Ensure the electrical supply is isolated and the gas supply is off.
2. Release the two screws securing the control panel and lower the panel.
3. Remove the four screws securing the front case. Lift the case up and forwards to remove.
4. Disconnect the gas supply pipe union from the manifold.
5. Remove the two screws securing the air supply pipe and remove the pipe.
6. Release the two screws securing the fan assembly to the combustion chamber front.
7. Remove the two pressure tubes, noting their positions.
8. Disconnect the electrode lead from the ignition generator and the in-line connector to the flame sensing electrode.
9. Remove the four nuts and washers and four screws securing the combustion chamber front assembly and remove the
assembly.
Fig. 7.1
Front case locating pins
Front case fixing screws
Combustion chamber
front assembly
Gas pipe union
Air supply pipe
fixing screw
Air supply pipe
fixing screw
Air supply pipe
Pressure tube
connections
Viewing window
Four nuts and washers
and four screws
securing combustion
chamber front assembly
Flue gas
sampling point
Fan assembly
fixing screws
Fan assembly
Manual air vent
Expansion vessel
test/fill point
Ignition generator
Flame sensing
electrode
5. Refill, vent and re-pressurise the system as necessary. (Refer to Commissioning, Section 6.1).
If the system pressure exceeds 2.5 bar when operating at maximum temperature, the heating expansion vessel should
be checked and re-pressurised, if necessary.
Note: 1.
Check the expansion vessel charge only when the system pressure is zero.
2.
The expansion vessel pressure test point is accessible from inside the boiler at the front.
6. Check that the condensate trap drain pipe is connected and all joints are sound.
7. Record details of the service in the Service Record at the back of these instructions.