KM 255 en
Start-up/Shutdown
V1.0
29
Caution
Observe arrow for the pressure valve (for flow direction)!
7.2.4
Start-Up/Subsequent Start-Up
1. Connect the electrical power supply.
2. Depending on the installation, start the pump where possible without counterpressure.
See installation example for easy deaeration of the dosing head in the section on ’Installa-
tion’.
3. Set the stroke adjustment button (L) to 0 %.
4. Run the pump for approx. 5 minutes.
5. Checking the oil level.
5.1 Set the stroke adjustment button (L) to 40 %.
5.2 Run the pump for approx. 10 minutes with a stroke adjustment of 40%.
5.3 Switch off pump, check the oil level and add oil if necessary.
5.4 Fit the oil filling screw (F) and the oil-level gauge back on.
–
The pump is now ready to operate.
Note
The rod length of the oil level gauge is
Caution
Check the oil level at least every 2 weeks and add oil if necessary.
Only use original ALLDOS gear oil!
7.2.5
After start-up
Caution
Following initial start-up and after each time the diaphragm is changed, tighten the
fixing screws on the dosing head:
After approximately 6 - 10 working hours or two days, tighten the dosing head
screws crosswise using a torque wrench.
Torque:
1q Dosing head screws
2
Dosing head
3b Pressure valve
F Oil filling screw
L
Stroke adjustment button
1l Cover for stroke adjustment
button
M Pressure relief valve
L
F
1l
2
M
M
1q
3b
for KM 255
35 mm; immersion depth to marking approx. 5 mm.
Pump Type
Order No.
Description
KM 255
single
555-302
3,5 l DHG 68
KM 255
double
555-303
4,5 l DHG 68
50 - 54 Nm for KM 255