AirSynergy3 Equipment Installation Guide
Page 47 | Commercial in Confidence SYN-UG-018
7 Appendix A
7.1 Review
Job Sheet
The
Job Sheet
should include the following information:
Pole for installation identified
Position on pole identified
Pole access restrictions (highway regulations, other services on pole, power pole)
Method of reaching pole positions (ladders, Elevated work platform)
AC main fuseway available for PSU
Configuration programming details known
Point of connection for Ethernet (if applicable)
All equipment items available at the installation site
o
Main AirSynergy unit
o
Mounting bracket and pole clamps
o
PSU
o
PoE injector (with fixing kit)
o
Ethernet cable assembly
o
GPS Antenna
o
GPS antenna installation kit
o
Front sector Antenna (if applicable)
o
Front sector Antenna mounting bracket ad fixing kit (if applicable)
o
External panel antenna (if applicable)
o
RF feeder cable tails (if applicable)
Required tools
o
Large flat screw driver for pole clamps
o
Small flat screwdriver for PoE power terminations
o
Small cross-head screwdriver for PoE box lid and fixings for PoE injector and
PSU
o
20mm wrench or small pipe wrench for RF connections
o
10mm wrench for main unit mounting flange nuts
o
Side cutters
o
Wire strippers
o
Krone punch down tool
o
Tilt meter to set antenna downtilts
o
Ring terminals crimp tool
Required ancilliary equipment
o
Lap top PC for initial configuration
o
Ethernet cable for temporary connection of the lap top
Other install materials
o
Self amalgamating
o
Black PVC tape
o
Cable ties
o
Labels
Whether the system is required to be locked to a GPS timing reference
.
A BSID is required for each AirSynergy
. This should be in a format xxxxxx:xxxxxx where x
is a decimal digit.
Network configuration information for the SDR blade
. This shall include the following
information for the front panel and the backplane.
IP Address:
Should only be set if Management IP Mode is set to Static IP Address. See
below for Management IP Mode parameter.