Section 6: VMB Functional Checklist
Revision A: July 1995
Page 6 - 5
AIR PRODUCTS VALVE MANIFOLD BOX FIELD START-UP CHECKLIST
page 2 of 6
ELECTRICAL
Check off line item when completed
Sign and date when section is completed
Branch A-D Left
Branch E-H Right
Earth ground installed
120v/240v electrical complete (circle)
Graphics panel condition satisfactory
Elect. sealoffs poured
I/O wired per DWG # EE-_______ series
Verify heat tape power
SECTION COMPLETED SIGNATURE___________________ DATE ________
CONTROLLER
Branch A-D Left
Branch E-H Right
Seat all circuit boards and eproms ( caution:
remove power before removing eproms or circuit
boards)
E-stop guard in place
All pneumatic valve graphics illuminating
Remove pneumatic bulkheads from the back of the controller.
Do all valves operate ?
Manual mode operation
No audible solenoid leaks
Re-install pneumatic bulkheads from the back of the controller.
Verify correct CPU eprom
VERS.# __________
Verify correct I/O eprom
VERS.#________
Verify correct BIOS eprom
VERS.#________
External Shutdown wired
Supervisory circuit utilized
Correct program loaded / version
Program name and date
Life safety system utilized ( yes / no )
Life safety system contact N.O. ( yes / no )
Barriers installed per controller item # verification
SEMC See attached Gasguard inspection and test sheet
Shorting blocks per controller item # verification
SEMC See attached Gasguard inspection and test sheet
Verify port and loop # indicated on the controller
Network addressed
VMB name ____________
Port number _____________
Loop number _____________
VMB communicating with network
Controller door adjustment
Z - purge set @
≥
0.1" H2O
SECTION COMPLETED SIGNATURE_________________ DATE ________
Содержание Gasguard 250
Страница 3: ......
Страница 9: ...Gasguard 250 VMB System Installation Manual Air Products and Chemicals Inc Page i 2...
Страница 50: ...Gasguard 250 VMB System Installation Manual Air Products and Chemicals Inc Page 5 6...
Страница 60: ...Gasguard 250 VMB System Installation Manual Air Products and Chemicals Inc Page 6 10...
Страница 68: ...Gasguard 250 VMB System Installation Manual Air Products and Chemicals Inc Page A 8...