G-46
Z-106164_EN ● 00
C
ommissioning
c
ommIssIonInG
Filling the Tank
Condition(s):
OFF
Tank flushed with fresh water.
Filling procedure:
Primary tank:
1.
Fill the primary circuit through the primary cir-
cuit supply connection (inlet).
2.
Bleed the air from the primary tank and re-
peat water filling until you reach desirable
pressure.
The water pressure must be the same
as in the hydraulic system design, but
not less than 1 bar.
Follow-on Task(s):
î
Check that there are no leaks
î
Start the appliance as required. Refer to the
Start-up
procedure opposite.
i
Start-up and Commissioning
Conditions:
Procedure:
1.
Make sure that all connections are tight and
there is no leak.
2.
Push the On/Off switch located on the right
side of the appliance.
î
When in the ON position, the
switch remains pushed in and is
illuminated.
î
When starting the appliance for the
first time after installation, the con
-
troller will open the Commissioning
Wizard automatically. This wizard pro-
cess only appears once, provided that
the function is disabled (set to “off’)
at completion of the process. To by-
pass it, activate “Continue” or “Skip”
displayed at the bottom of the screen,
until you reach the end of the process.
3.
If required, perform the commissioning set-
ting of the appliance, following the instruc-
tions displayed on the screen. Refer to
“Commissioning Wizard” on page G-47
for more information and a list of the settings.
Follow-on task(s):
None.
i
The tank does not have a pressure
sensor.
The system should be equipped with
a sensor so that the tank can be filled
based on its readings.
Содержание TMU 500
Страница 45: ...G 45 Z 106164_EN 00 Product Installation Fig 23 Wiring heat pump circulating pump Fig 24 TMU wiring Boiler...
Страница 65: ...G 65 Z 106164_EN 00 NOTES...
Страница 66: ...G 66 Z 106164_EN 00 NOTES...
Страница 67: ...G 67 Z 106164_EN 00 NOTES...
Страница 68: ...www myaic eu AIC Europe B V Graafschap Hornelaan 163A NL 6001 AC Weert The Netherlands...