Instrument Installation Checklist
Revision:
A.00
, Issued:
January
17
, 20
21
Document part number:
D0007550
Page ____ of ____
© Agilent Technologies, Inc. 20
21
8
Verify the installed drawer and sides of the enclosure are aligned and parallel and adjust, if
necessary.
a
Measure the gap between the front motor cover and the enclosure internal wall at the
bottom of the cover and at the top at the upper mounting screws.
b
If the difference between the top and bottom measurements is greater than 3-mm, the tilt
of the drawer will need to be adjusted using spacers. If the drawer does not need to be
Routing and connecting enclosure cables
to continue with the installation.
Adjusting the tilt, if necessary
1
Determine which correction size spacer to use:
If the drawer tilt is 3-5-mm, use the 3-mm side of the correction spacers.
If the drawer tilt is >5-mm, use the 6-mm side of the correction spacers.
2
Determine which side of the enclosure to insert the spacers:
If the drawer leans to the left (the gap is smaller at the top on the left side) as you face the
front of the enclosure, you will replace the left two white O-ring cups (underneath the
elevator mounting screws) with the lean correction spacers, provided in the installation kit.
If the drawer leans to the right (the gap is smaller at the top on the right side) as you face
the front of the enclosure, you will replace the right two O-ring cups (underneath the
elevator mounting screws) with the lean correction spacers, provided in the installation kit.
3
Adjust the tilt:
a
Locate the correction spacers (P/N G9532-20167, G9532-20168) and the adjuster screw
(P/N 0515-0436).