9. Plug the UPS power cord into the utility power cord inlet on the UPS.
10. Plug the UPS power cord into the wall outlet. (The UPS battery charges when it is
connected to the utility power. The battery charges fully during the first 24 hours of
normal operation. Do not expect full battery run capability during this initial charge
period.)
11. Verify indicator lights are in agreement with manufacturer specifications and the unit is
functioning.
5.3.6
Fiber Splice SC/APC Bulkhead NID (P/N: 1187770G1) Installation
A fiber connection is required between the inner GPON 452/454 enclosure and the fiber
termination point in the Outer Enclosure. This may be achieved by using the provided fiber
jumper. To install the fiber connection, perform the following steps:
Remove the dust cover from one end of the fiber jumper and attach it to the incoming fiber
jumper at the SC/APC Bulkhead connector (see
).
1. Connect the fiber cable coming into the Splice Housing to the Bulkhead Connector.
2. Route the fiber jumper from the Bulkhead connector to the connection on the bottom of
the Electronics Module as shown in
. Ensure that this cable is not pinched when
the Electronics Module is closed.
3. Close the Electronics Module and secure by tightening the “Inner Security Screw” (see
Figure 16. Fiber SC/APC Bulkhead Installation
5
Signal Return
Green
6
12 V Return
Black
7
+12 VDC
Red
Table 8. UPS Pin-Out Connection
PIN
Description
Color
Fiber Connection
Ground Connection
Power Connection