16
Testing the Installation
Power-up and Initial Test Procedure
When the Accord control panel has been installed in accordance with the preceding
safety and wiring instructions the system should be tested. The test procedure is outlined
below.
Note: Before the test commences all auxiliary devices such as powered sensors
(PIRs), remote keypads, alarm sounders, etc, must be connected. The stand-by
battery should not be connected at this point.
Apply input power to the mains transformer. Check that the Auxiliary Voltage at terminals
AUX + and AUX – on the main terminal strip measures between 13.5 V and 14 V d.c. If
the auxiliary voltage is under 13.5 V, too much current is being drawn. For the current
consumption of the control panel and keypads see Appendix A.
Note: If the auxiliary voltage is between 13.5 V and 14 V d.c., connect the battery to
the Battery Terminals, observing the correct polarity.
Further Test Procedures
Once the control panel has been installed, and the power up and initial test procedure
have been performed, it is advisable to check that the keypad(s) and ancillary devices are
operating correctly.
To test the keypad:
1.
Press 1234 1 – Set.
2.
Press
Ö
(Escape) – Exit Panel Set.
This ensures that the keypad and control panel are communicating correctly. Test each
keypad in this manner. See Section 4 for test information.
Walk Test Zones:
It is advisable to Walk Test all programmed zones, including RF zones and any zone
added after initial Power-Up.
Engineer Digicom Test:
This test allows the enigeer to send a test report through the digicom. Two beeps con-
firm entry of key sequence whilst a further two beeps confirm kiss off.
To send Test Report:
1.
Press Engineer Code, # then 5.
Содержание ACCORD XPC
Страница 1: ...Installation Manual ...
Страница 2: ......
Страница 12: ...6 ...
Страница 48: ...42 ...
Страница 56: ...50 ...
Страница 61: ...55 Accord xpC July 2001 ...
Страница 62: ...56 IE1 1230 63 Issue D ...