08 COMMISSIONING
3BHS213401 E01 REV H
ACS1000 AIR-COOLED
USER MANUAL
109/184
8.1
Overview
The following sections provide an overview of the commissioning process for your drive.
8.1.1
Required qualification
8.1.2
Commissioning procedure
8.1.3
Commissioning checklist
8.1.4
Customer assistance
8.1.5
Customer acceptance
Commissioning, parameter adjustments and functional tests of the drive must be
carried out only by commissioning personnel certified by ABB.
Information on the commissioning procedure and the start conditions for
commissioning can be obtained from ABB.
In order to ensure uncomplicated and speedy commissioning, it is important that
drive and associated equipment are ready for commissioning. Reviewing and
completing the items in the “8.2 Commissioning checklist” on page 110 before the
commissioning personnel arrive on site will help to achieve this.
During the commissioning period, the customer is requested to provide qualified
personnel for assistance, who are:
- Experienced with medium and low voltage equipment and with the local
safety regulations
- Familiar with the driven process
- Authorized to operate associated medium and low voltage equipment (eg, main
circuit breaker, other low and medium voltage switchgear)
- Authorized to operate the driven process for functional tests
When commissioning has been completed, the commissioning report is signed by
the responsible commissioning personnel and by the customer as a sign of
acceptance. A copy of the report and a copy of the actual parameter settings are
handed out to the customer.
Содержание ACS 1013-A1
Страница 1: ... MEDIUM VOLTAGE AC DRIVES ACS1000 air cooled User manual ...
Страница 3: ...Contents ACS1000 air cooled User manual ...
Страница 5: ... 01 About this manual 01 3 14 ...
Страница 16: ......
Страница 17: ... 02 Important safety information 02 15 26 ...
Страница 28: ......
Страница 29: ... 03 Power electronics and cabinet features03 27 50 ...
Страница 53: ... 04 Control system 04 51 66 ...
Страница 68: ......
Страница 69: ... 05 Transportation storage and disposal05 67 74 ...
Страница 76: ......
Страница 77: ... 06 Mechanical installation 06 75 82 ...
Страница 84: ......
Страница 85: ... 07 Electrical installation07 83 106 ...
Страница 108: ......
Страница 109: ... 08 Commissioning 08 107 112 ...
Страница 115: ... 09 Operation 09 113 126 ...
Страница 129: ... 10 CDP control panel 10 127 150 ...
Страница 153: ... 11 Preventive and corrective maintenance 11 151 182 ...
Страница 185: ......