Installation
45
Powerware
®
Prestige Series Installation and Operator’s Manual for IBM Applications (3000 VA)
Uncontrolled Copy
1.
Place the conduit through the access hole on the junction box
(see Figure 10). Connect the exposed conduit wires to the
corresponding compression terminals (see the following table).
Tighten the compression terminals with a screwdriver.
2.
Pivot the REPO receptacle guard out of the way, plug the REPO
plug/receptacle UPS connector into the REPO receptacle on the
UPS rear panel and twist the connector in place (see Figure 5
on page 37).
Mounting Holes
Plug/Receptacle
UPS Connector
Three Foot Cord
Terminal Block
Access Hole
for Conduit
Figure 10. Optional REPO Cord Junction Box
Power Cable Terminations
Tightening Torque
Wire Function
Terminal
Position
Terminal Wire
Size Rating*
Entrelec
Phoenix
Contact
REPO
L1
TB1-4
L2
TB1-5
12 - 22 AWG
(4 - 0 mm
2
)
3.5 - 5.3 lb in
5.6 - 6.8 lb in
Ground
TB1-6
(4 - 0 mm
2
)
*
Suggested wire size is #18-AWG (0.75 mm
2
) 75
C copper wire minimum.
NOTE
The REPO function activates when L1 and L2 are shorted together.