After replacing a cylinder or after making a
gas connection, perform a leak test
to check for
gas leaks between regulator and cylinder, and between regulator
and braided hose.
Stage 1
1. Turn the gas off.
2. Using soapy water applied with a sponge, or with a
brush, cover all of the gas joints with a liberal
amount of suds.
Stage 2
1. Turn the gas on.
2. Inspect the joints for leaks.
3. If any bubbles appear to grow, the joint will need to be
resealed and tested again.
CO
2
Regulator
Leak Test
Note
When removing hose, take care not to
lose plastic olive from the fitting.
3.1 Braided hose fitting
Install the mains water braided hoses to the Command-Centre
TM
before locating in place.