Page 10 of 20
804050UK G4 Commercial chilled and sparkling installation instructions - Sept. 2016 - v3.02
Before installation
Before installation ensure that the following have been
provided at the installation site
•
Review of all the technical specifications.
•
Ensure the under counter cupboard floor can support the product weight
when full of water (allow an extra 5-8kg when full).
•
Sufficient space in the cupboard to install the Command-Centre
TM
and
other components in accordance with these installation instructions. See
technical specification, page 9 for dimensions.
•
For Zip HydroTap
®
G4 Chilled and sparkling only models, 1 x 220-240V AC
13A socket will be required.
•
The Command-Centre
TM
must be installed in accordance with IEE
regulations. See Technical specification, page 9 for power ratings.
Note
Check all cable and hose lengths against inlet /outlet positions before
proceeding (see sections 2 & 3 pages 13 to 16 for general layout).
•
A potable water supply connection with isolating valve inside the
cupboard within reach of the braided hoses and positioned so that the
connection point and the stop cock will not be obstructed when the
Command-Centre
TM
is installed.
•
A potable cold water supply with a minimum working pressure of:
(see page 9 min. / max. water supply pressure).
•
For Celsius models, a sepatare hot mains water supply and isolation
valve is also required.
•
If pressure is likely to exceed 0.7 MPa (7 bar), install a 0.35 MPa (3.5
bar) pressure limiting valve.
•
The appliance must be placed with its base in a horizontal position.
IMPORTANT!
Do not proceed with the installation if these requirements are