Doc Number 801-00015, Version 1.1, Copyright © 2010 Zep Solar, Inc.
PAGE:
19 of 28
ZEP SYSTEM II INSTALLATION MANUAL
5.9 > Leveling the Row
1. Once the row has been completed, attach all the Leveling Feet on the upper row to the roof or to
their respective attachment hardware.
2. Next, use a laser level, string line or careful eye to determine if height adjustment is necessary
(Figure 5.9A). Use the Zep Tool or a drill with a T30 Torx bit to raise (
counter-clockwise
) or lower
(
clockwise
) the height at the Leveling Foot (Figure 5.9B).
Figure 5.9A
Figure 5.10A
Figure 5.9B
Figure 5.10B
5.10 > Drop in and Pivot Lock Procedure
1. Moving up to the next row, rest the edge of the next Module on the top of the Foot Zeps (Figure 5.10A).
In order for the Zep tongue to fully seat into the Module groove, the Module should cover about
half of the top of the foot stud prior to starting the drop in and pivot lock procedure (Figure 5.10B).