ZEP SYSTEM I INSTALLATION MANUAL
Copyright © 2012 Zep Solar, Inc.
PAGE 17 OF 50
3-C: Mount Spanner Bars to tile hooks.
Use one 9/16” carriage bolt and flange
nut per sleeve/tile hook.
Tighten nut and bolt to snug tight.
3-D: Install the remaining Spanner Bars.
Repeat Steps 3-A through 3-C for each
remaining column (landscape) or row
(portrait) of Spanner Bars.
Use a string line to align the front ends
of the Spanner Bars.
3-E: Install the first Cam Foot.
Insert Cam Foot into Spanner Bar
approximately 1” from the end.
The Key side of a Cam Foot (A) always
snaps into a module or Array Skirt
while the Tongue side (B) always
accepts a module during drop-in.
A
B