33/50
User Manual for HYD 3-6 kw ES Hybrid Inverter - Rev. 1.1 del 13/06/2019
Identificazione: MD-AL-GI-00
Rev. 4.0 del 31.01.18 - Applicazione: GID
3.
Photovoltaic Input Mode
Photovoltaic Input Mode selection: The HYD-ES inverter has two MPPT channels. The two MPPTs can operate
independently or in parallel. If the PV strings are connected in parallel, “parallel mode” must be selected
before connecting to the inverter; otherwise the default configuration (independent mode) must be used.
After changing the PV input mode, restart the HYD-ES inverter to validate this change.
4.
EPS Mode
The EPS mode allows enabling the EPS output for critical loads.
5. Select EPS mode
1.EPS control mode
1.Enable EPS mode
2.Disable EPS mode
5.
Communication address
Select “6. Communication Address selection”, then press “OK”. Press “Up” or “Down” to change the first digit,
press “OK” to move to the next one. After changing the communication address-485 (
default: 01)
, press “OK”.
6.
Self-test (ONLY for the Italian market)
Select “7. Self-test” and press “OK” to enter the self-test interface.
7.Self-Test
1.Fast self-test
2.STD Self-test
3.QF time setting
3.QV time setting
5.Control 81.S1
1)
Fast self-test
Select “1. Fast self-test,” then press “OK” to start the fast self-test.
Start Self-Test
↓
Press “OK” to start
Testing 59.S1...
↓
Wait
Test 59.S1 OK!
↓
Wait
Testing 59.S2...
↓
Wait
Test 59.S2 OK!
“Up” ↑
“Down” ↓