Check that the value of the consumption remains
constant* as the power supplied by the battery
increases during discharge.
Check that the power taken
from the grid decreases by an
amount equal to the power
supplied by the battery.
Once the photovoltaic system has been activated, check that:
The value of consumption remains constant as the
photovoltaic power increases.
Depending on the photovoltaic production, the system will
operate according to the mode described in chapter 6.
Note
: If the conditions described above are not met:
•
Unfreeze the current sensors as described in point 12.2 of this guide.
•
Check the correct positioning of the current sensors and then restart the system by
performing the above checks, and freeze the sensors only after making sure that
everything has been installed correctly.
Once the countdown is over, the batteries will start to deliver
power to the utility according to availability, and will attempt
to reset the consumption from the grid.
* Check that the power of the loads in use does not change:
•
Heat pump or pump → Load variable over time
•
Light or Hairdryer → Load constant over time
NA
NA
OFF
OFF
OFF
OFF
Hybrid Inverter
ON
GRID
ON
ON
Switch the photovoltaic system back on by turning
the DC switch to the ON position