INSTALLATION AND ELECTRICAL CONNECTIONS
1) Level
the machine.
You can use a depth or feet if contained in the machine kit.
Remove the
side external covers (a)
of the machines loosing the two bolts (Top and
down of the side (b)), and the linking clamp.(See Picture n°1)
2) Assembling of input-output benches
Working in the back side of the machine, unscrew a little the back screw (a) (the not
painted one 16 mm diameter (See Picture 2a - 2b)
ATTENTION: Do not use the longer painted screw . It has already been correctly
positioned during the running test.
Position the input-output racks (paying attention not to damage the two conic gears (c)),
so that the top of two opposite screws (a) will be correspondent at the center of the front
pulley. We suggest to use supports of proper height (at the same level of the working
racks) which
will be positioned to the top of the racks and placed in balance (See
Picture 2b).
Always working in the back side of the machine, screw again the back screw jamming it
with the lock nuts(b).