2. Air purging by refrigerant
Procedure:
1). Confirm that both the 2-way and 3-way valves are set to the closed position.
2). Connect the charge set and a charging cylinder to the service port of the 3-way valve.
3). Air purging.
Open the valves on the charging cylinder and the charge set. Purge the air by loosening the flare nut on the
2-way valve approximately 45’ for 3 seconds then closing it for 1 minute; repeat 3 times.
After purging the air, use a torque wrench to tighten the flare nut on the 2-way valve.
4). Check the gas leakage.
Check the flare connections for gas leakage.
5). Discharge the refrigerant.
Close the valve on the charging cylinder and discharge the refrigerant by loosening the flare nut on the 2-
way valve approximately 45’ until the gauge indicates 0.3 to 0.5 Mpa.
6). Disconnect the charge set and the charging cylinder, and set the 2-way and 3-way valves to the open
position.
Be sure to use a hexagonal wrench to operate the valve stems.
7). Mount the valve stems nuts and the service port cap.
Be sure to use a torque wrench to tighten the service port cap to a torque 18N
·
m.
Be sure to check the gas leakage.
Summary of Contents for YU2E14YEEBMHO-X
Page 8: ...7 5 Wiring diagram YU2E14YEEBMHO X YU2E18YEEBMHO X...
Page 10: ...9...
Page 11: ...10 YU4E28YEEBMHO X YU4E36YEEBMHO X...
Page 12: ...11 YU5E42YEEBMHO X...
Page 34: ...33 10 3 1 2 Indoor outdoor units communication error...
Page 39: ...38 10 3 1 4 Open or short circuit of temperature sensor 10 3 1 5 Full water malfunction...
Page 42: ...41 10 3 3 2 Communication malfunction between IPM board and outdoor main board ODU E3...
Page 45: ...44 10 3 3 5 High pressure protection ODU P1 ForYU4E28YEEBMHO X YU4E36YEEBMHO X YU5E42YEEBMHO X...
Page 47: ...46 10 3 3 7 Current protection of compressor ODU P3...
Page 48: ...47 10 3 3 8 Temperature protection of compressor discharge ODU P4...