New Release 

START-UP

START UP-UP CHECKLIST

FAN INSPECTION

     ❑

   

Remove or loosen all shipping bolts on fan assembly.

     ❑

   

Tighten set screws on pulleys, bearings and fan, if applicable. 

     ❑

   

Check tightness of fan bearing bolts, if applicable.

     ❑

   

Check tightness of blower wheel and fans to shaft.

     ❑

   

Check tightness of fan and motor sheaves, if applicable.

     ❑

   

Check tightness of all motor base and mounting bolts.

     ❑

   

Check sheave alignment - adjust if required.

     ❑

   

Adjust belt tension per sticker on fan blower assembly.

NOTE: Use “O” ring type defl ection belt tension checker.

     ❑

  

Equipment received as ordered.

     ❑

  

Unit checked for damage interior and exterior.

     ❑

  

Make sure all ductwork is complete and available for full air fl ow.

     ❑

  

Unit installed with proper clearances.

     ❑

  

Installer has cleaned out interior.

     ❑

  

Clean air fi lters installed properly and secured.

     ❑

  

Controls installation complete

     ❑

  

Rotate all moving components manually.  Adjust as required.

     ❑

  

Check all electrical connections for tightness.

     ❑

  

Review electrical print for correct wiring.

     ❑

  

Check condensate drain trap. 

     ❑

  

Main coil drain pan and auxiliary fl oor drains must be properly trapped and charged with water before units are started.

NOTE: If the motor and fan have not been operated in the last (4) four weeks or more, lubricate all the bearings and rotate the motor and fan 

monthly to prevent moisture from accumulating in the bearings. (See Form 50.20-NM3, Long Term Storage)

ADJUSTMENT FOLLOWING INSTALLATION

The following adjustments should be made after 
installation:

• Blower Speed Adjustment

  Adjustment of blower speed is made by loosening 

the set screw in the outer (movable) pulley face 
and turning this face half or full turns only, so that 
the adjusting set screw will be positioned precisely 
over the fl at on the pulley hub.  Speed is reduced by 

adjusting the pulley faces so that they are further 
apart; speed is increased with faces closer together.  
Check all of the pulleys’ set screws for tightness.

• Room Thermostat

  Adjust room thermostat to desired temperature.  

This depends upon the environment and the 
individual.  For peak load conditions, the ideal 
thermostat setting for “winter” and “summer” is 
72°F and 76°F respectively.

YORK INTERNATIONAL

8

FORM 115.22-NOM5 (704)

Summary of Contents for YSHW

Page 1: ...ION RECORD THE UNIT MODEL AND SERIAL NO IN THE SPACE PROVIDED RETAIN FOR FUTURE REFERENCE Model No _____________________ Serial No ___________________ INSTALLER S RESPONSIBILITY Installer Please Note...

Page 2: ...lding construction provisions for mounting the unit must be made by the contractor according to architects drawings Before mounting unit remove red headed shipping bolts and metal bush ing at blower b...

Page 3: ...in the proper level This will ensure that the condensate will drain from the unit POWER WIRING All wiring must comply with the local and national code requirements Units are provided with wiring diagr...

Page 4: ...valves throughout the building CONTROL WIRING These blower coil units can be provided with an optional class 2 relay transformer for 24 volt control circuits 3 4 HP maximum load rating Should any add...

Page 5: ...12 1 4 10 7 8 27 1 2 16 1 4 16 X 16 3 7 8 ODS 48YSHW6 39 43 1 2 38 22 7 8 13 5 8 11 7 8 29 20 1 4 16 X 20 3 7 8 ODS 60YSHW6 42 50 1 2 45 22 7 8 16 13 7 8 36 20 1 4 20 X 20 2 1 1 8 ODS 4 ROW COIL FILT...

Page 6: ...19 1 8 48 30 1 4 26 X 29 2 1 3 8 ODS 180YSHW6 56 1 2 66 39 1 2 16 3 8 44 3 4 57 37 3 4 20 X 36 5 3 1 3 8 ODS 240YSHW6 62 1 2 66 52 16 3 8 44 3 4 57 50 1 4 20 X 49 3 1 3 8 ODS 4 ROW COIL FILTER SIZE L...

Page 7: ...packed Replace if required Inspect the thrust collars for end play and alignment of wheel Check the blades for accumulations of dirt and clean in order to avoid imbalance and vibration Check mounting...

Page 8: ...just as required Check all electrical connections for tightness Review electrical print for correct wiring Check condensate drain trap Main coil drain pan and auxiliary floor drains must be properly t...