JOHNSON CONTROLS
31
FORM 150.73-NM1
ISSUE DATE: 09/04/2020
4
To ensure warranty coverage, this equip-
ment must be commissioned and serviced
by an authorized Johnson Controls
service mechanic or a qualified service
person experienced in equipment instal-
lation. Installation must comply with all
applicable codes, particularly in regard to
electrical wiring and other safety elements
such as relief valves, HP cutout settings,
design working pressures, and ventilation
requirements consistent with the amount
and type of refrigerant charge.
Lethal voltages exist within the control
panels. Before servicing, open and tag
all disconnect switches.
INSTALLATION CHECKLIST
The following items, 1 through 5, must be checked be-
fore placing the units in operation.
1. Inspect the unit for shipping damage.
2. Rig unit using spreader bars.
3. Open the unit only to install water piping sys-
tem. Do not remove protective covers from water
connections until piping is ready for attachment.
Check water piping to ensure cleanliness.
4. Pipe unit using good piping practice (refer to
ASHRAE handbook section 215 and 195
).
5. Check to see that the unit is installed and operated
within limitations. See
.
The following pages outline detailed procedures to be
followed to install and start-up the unit.
HANDLING
These units are shipped as completely assembled units
containing full operating charge, and care should be
taken to avoid damage due to rough handling.
LOCATION AND CLEARANCES
These units are designed for outdoor installations on
ground level, rooftop, or beside a building. Location
should be selected for minimum sun exposure and to
SECTION 4 – INSTALLATION
ensure adequate supply of fresh air for the condenser.
The units must be installed with sufficient clearances
for air entrance to the condenser coil, for air discharge
away from the condenser, and for servicing access.
In installations where winter operation is intended and
snow accumulations are expected, additional height
must be provided to ensure normal condenser air flow.
Clearances are listed under “Notes” in
Foundation
The unit should be mounted on a flat and level founda-
tion, floor, or rooftop capable of supporting the entire
operating weight of the equipment. See
for operating weight. If the unit is elevated
beyond the normal reach of service personnel, a suit-
able catwalk must be capable of supporting service
personnel, their equipment, and the compressors.
Ground Level Locations
It is important that the units be installed on a substan-
tial base that will not settle. A one piece concrete slab
with footers extended below the frost line is highly rec-
ommended. Additionally, the slab should not be tied to
the main building foundations as noise and vibration
may be transmitted. Mounting holes are provided in
the steel channel for bolting the unit to its foundation.
See
Dimensions (English) on page 84
For ground level installations, precautions should be
taken to protect the unit from tampering by or injury to
unauthorized persons. Screws and/or latches on access
panels will prevent casual tampering. However, further
safety precautions such as a fenced-in enclosure or
locking devices on the panels may be advisable.
Rooftop Locations
Choose a spot with adequate structural strength to
safely support the entire weight of the unit and service
personnel. Care must be taken not to damage the roof.
Consult the building contractor or architect if the roof is
bonded. Roof installations should have wooden beams
(treated to reduce deterioration), cork, rubber, or vibra-
tion isolators under the base to minimize vibration.
Summary of Contents for YLUA0078
Page 10: ...JOHNSON CONTROLS 10 FORM 150 73 NM1 ISSUE DATE 09 04 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 14: ...JOHNSON CONTROLS 14 FORM 150 73 NM1 ISSUE DATE 09 04 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 42: ...JOHNSON CONTROLS 42 FORM 150 73 NM1 ISSUE DATE 09 04 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 100: ...JOHNSON CONTROLS 100 FORM 150 73 NM1 ISSUE DATE 09 04 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 130: ...JOHNSON CONTROLS 130 FORM 150 73 NM1 ISSUE DATE 09 04 2020 THIS PAGE INTENTIONALLY LEFT BLANK...
Page 152: ...JOHNSON CONTROLS 152 FORM 150 73 NM1 ISSUE DATE 09 04 2020 THIS PAGE INTENTIONALLY LEFT BLANK...