3-7
IM AQ1210-01EN
Performing Real-time Measurement
11
22
33
44
55
66
77
88
99
10
10
11
11
App
App
Index
Index
3.3 Cable Installation Completion Notification
Procedure
Soft Key Menu (Work Completion Notice)
1.
Tap the soft key menu display button (when real-time measurement is not in progress).
Finishing real-time
measurement
Configure the work
completion notification.
2.
Tap the
Advanced Measurement
soft key and then the
Work Completion Notice
soft key.
The Work Completion Notice screen appears.
Set the notification (OFF, ON).
Set the message display at work completion
(OFF, ON).
Set the confirmation message
(No Check, Check only once, Check everytime).
Set how to display the message confirming
whether you have moved the cursor to the work
completion point.
Set the alarm sound at work completion
(OFF, ON).