5
Installation Specification of Guyed Tower
Step 1: Choosing Installation Sites
The wind turbine should be erected high and far away from obstacles as possible in order to get
relatively high wind speed. Meanwhile soil quality of installation location should be taken into
consideration. Loose sands, uneven or easily influenced by weather condition areas should be
excluded from installing the wind turbine. When selecting the locations, it’s necessary to
consider the distance between generator and pile. The shorter the distance is, the less cable
would be used. As a result, less energy waste would be produced during the transmission.
While under the circumstances of longer distance, it’s better to use much thicker standard
cable for the transmission.
Step 2: Layout of Tower, Base & Anchor (as shown in the following tables)
Model
200W
300W
500W
1000W
2000W
Semi diameter(m)
2.0
3.0
3.0
3.0
4.0
Size of central base(m) (long*wide*deep)
0.4*0.4*0.3
0.5*0.5*0.4
0.6*0.6*0.5
Size of side base (m) (long*wide*deep)
0.3*0.3*0.3
0.4*0.4*0.3
0.5*0.5*0.4
Model
3000W
5000W
10KW
20KW
Semi diameter (m)
4.0
6.0
6.0
8.0
Size of central base (m) (long*wide*deep)
0.8*0.8*0.8
1.0*1.0*1.0
Size of side base (m) (long*wide*deep)
0.6*0.6*0.6
1.0*1.0*1.0
Table 1