4.1 Preparation before installation
The product is delivered to a warehouse by a logistics company and handed over to the
customer. Normally, XCHARGE is not responsible for transporting the charger to the final
installation site. During Installation there will be XCHARGE Service Colleagues for guidance.
Before installation, please ensure following list well prepared.
Foot print of NZS is 2300 mm x 800 mm. The space requirement of NZS is calculated as
front at least 1.6m to open the front door and rear at least 0.5m to ensure tightening screws
and basic operation.
Name
Pieces
Usage
Forklift trucks
cranes
Anti-theft screw tools
Sockets
Insulated torque spanners
Herringbone ladders
Glass glue
Insulated gloves
Insulated floor mats
Expansion bolts
Leveling ruler
11
Safety helmet
6
3
12
1
1
1
1
1
1
1
1
1
5
1
Bolts
≥5T, for product unloading
≥5T, for lifting and installation
For safety during ESS installation
M12 fix metal base to concrete base
Check levelness
Check and mark torque values
Remove ropes for lifting
Sealing screw gap
For safety during ESS installation
1
2
4
5
7
8
9
10
12
13
14
No.
4pcs M12*35 for connection
between Metal base and charger
4pcs M12*100 for connection
between Metal base and ESS
4pcs M14*80 for leveling between
ESS and Charger
5pcs M12*150 Expansion bolts
Door security screw removal
Fastening of case and base screws
Removal and tightening of front
and rear door body screws
Protection against falling objects
and other dangerous impacts
1
Electric screwdrivers
1