22
Copyright | NZS Installation and Operation Manual
There is production tolerance during ESS and charger production. Assembly two part together might
result in superimposed tolerance, so that a slant gap will present between ESS and charger. To avoid
this, a separate leveling mechanism is designed for charger part. The installation must be metal base
first, then ESS, charger at last and leveling adjustment for charger after all installation finished.
Installation of charger and leveling steps are as follows:
Open the front and rear doors, and use a socket wrench to take out the four bolts con-
necting the equipment to the base, then close doors.
Climb up the man-ladder, connect the sling with the 4 rings on the top of charger
Lift charger part from the transportation base on the predetermined position of the
metal base, confirm the long through-holes on charger corresponding to holes on metal
base. Open the front and rear doors, use the M12 combination screws (4PCS) to fix
charger to metal base and tighten it with a socket. Confirm the torque of 96NM with the
help of torque wrench.
If there is gap between charger part and ESS, please adjust 4pc M14 screws till no
significant gap between ESS and charger. Tighten the screws and raise up the charger.
Then close front and rear doors.
Charger Installation
Hole for leveling
Hole for installation
on mental base
(Back side)
(Front side)