Load Sharing Module
Manual 02035
14
Woodward
Figure 3-1. Temporary CT Connections
3. Disconnect the phase “B” CT wires from terminals 6 and 7 and connect
these two wires together. Use a small screw and nut and tape the
connection.
4. Disconnect the phase “C” CT wires from terminals 8 and 9 and connect
these two wires together. Use a small screw and nut and tape the
connection.
5. Connect the two wires from the phase “A” CT to phase “A” input terminals 4
and 5.
Be prepared to make an emergency shutdown when starting the
engine, turbine, or other type of prime mover, to protect against
runaway or overspeed with possible personal injury, loss of life, or
property damage.
6. Start the engine and apply full load.
7. Measure the load signal voltage between terminals 22 and 23 and record
this voltage.
8. Shut the generator set down and reverse the phase “A” wires on terminals 4
and 5.
9. Start the engine and apply full load.
10. Measure the load signal voltage between terminals 22 and 23 and record
this voltage.
11. Shut the generator set down.
12. Remove the phase “A” CT wires from terminal 4 and 5 and connect the
phase “A” CT wires to the phase “B” input terminals 6 and 7.
Summary of Contents for 9907-252
Page 6: ...Load Sharing Module Manual 02035 2 Woodward Figure 1 2 Outline Drawing of Load Sharing Module...
Page 7: ...Manual 02035 Load Sharing Module Woodward 3 Figure 1 3 Block Diagram of Load Sharing Module...
Page 8: ...Load Sharing Module Manual 02035 4 Woodward...
Page 34: ...Load Sharing Module Manual 02035 30 Woodward...
Page 35: ......