All information, illustrations and technical specifications in this publication correspond to the latest version as per the
time of publishing. Constructions and designs are subject to modifications without prior notice.
13
2.0. Connecting
2.1. General
Ensure that the tyre pressure
of the vehicle tyres is
correct.
Please observe the following
when selecting the correct
mounting points (for the
installed parts):
1.
Lowest position of
tractor - frontal lifting
2.
Top position of tractor -
frontal lifting
3.
Clearance for the p.t.o shaft
4.
Enough clearance between
sweeping machine and ground
in order to overcome
obstacles (e.g. kerbs).
5.
Installed sweeping machine
must be in float position in
order to be able to adapt to
the unevenness of the ground.
6.
The protective cover of the
V-belt must be parallel to
the ground. Setting is made
via the tractor's upper link.
2.2.
INSTALLATION WITH STANDARD THREE-POINT LINKAGE CAT.1
The installation stand is as
standard equipped with category
I connection components.
•
U Insert and secure the lower
link to the installation
stand using suitable pin (A).
•
Insert and secure upper link
with plug (B) to suitable
bore hole of the installation
stand.
•
Mount the PTO shaft.
•
Raise sweeping machine with
front hydraulics.