WeCo Srl Italia
www.wecobatteries.com
4K4 PRO V 1.11 28-9-2021
STACK, MODULE PREPRARATION
For installation with the stack kit it is necessary to have at least two battery modules.
The feet installed on the lower side of each battery will be used to interlock the modules
Step1 : Unscrew the feet of the first battery and screw it on the left side on the battery using the M8 Screw removed before from
the original position
Step 2: It will be necessary to remove the feet from the second battery and install them on the right side of the first battery
following the same instructions.
Step 3: Lay the first module on the ground on its final position
Step 4: Stick the 4 rubber pads on the back side of the second module
From the screw bag of the Stack Kit take the 4 rubber pads and stick it on
the back side of the battery on each corner as shown on the picture
FIRST MODULE
ON THE GROUND
RUBBER FEET
RUBBER FEET