5
Initial operation
5.1
Commissioning - comments
The work described here may only be performed by appropriately trained,
specialist staff of a specialist company or by persons familiar with the operating
instructions. The systems installed must be inspected for appropriate installation
and tightness before commissioning.
Use the commissioning protocol in
Section 9.3 for the commissioning procedure.
The device is provided with factory settings when it is delivered. Adjust the
standard parameters to the desired operating mode during commissioning and
enter these values into the operating data sheet shown in
Section 9.4
5.2
Commissioning - procedure
Insert the safety connector into an appropriate mains socked and switch on the
device at the main switch
(Pos 15, Page 9)
.
ATTENTION !
The initial operation requires that the length of the dosing line is
entered at the touch panel, the pump is bled and disinfection is
performed.
Log in with your password as Technician 2 at User Level 3 for that purpose. (for
procedure see Section 6.3.1).
Enter the hose length:
Open the Settings
Dosing menu and enter the actually installed length of hose
at the display. The maximum permitted hose length is 30m!
Save the input with the SAVE button.