Transport to work site /Recommendations on compaction
T00995GB.fm
26
3.
Transport to work site /Recommendations on compaction
3.1
Transport to work site
Conditions:
∗
To transport the vibration plate, only use suitable lifting equipment with
a minimum load-bearing capacity of 500 kg.
∗
Always switch off engine before transporting the machine!
∗
Vertically set guide handle head and lock into place.
∗
Only attach suitable tackle at the central lifting point (18a) provided.
The central lifting point is located exactly above the centre of gravity of
the machine. The central lifting point can be displaced rearwards
(18b), given an application in which the height of the machine is of
importance (torque wrench setting = 85 Nm).
∗
During transport on the loading area of a vehicle, tie down the vibration
plate using the lugs (17).
Note: Also overve the regulations in safety instructions.
Summary of Contents for DPU 5545He
Page 1: ...Operator s Manual Vibratory plate DPU 5545He 0226267en 003 12 2010...
Page 23: ...Description T00994GB fm 23 2 Description 2 1 Dimensions 2 2 Max admissible inclination...
Page 46: ......
Page 47: ......
Page 48: ......