www.voestalpine.com/strassensicherheit
voestalpine Krems Finaltechnik GmbH
ONE STEP AHEAD.
Assembly instructions KB 1 RH3 on pile-drivable subgrade
page 6 of 13
Installation of the vehicle barrier system in accordance with data sheets B106/2
and B106/3 (see appendix)
It is not necessary to pre-assembly the vehicle barrier system components in the
factory.
Due to the fact that the vehicle barrier system is not pre-stressed, the ambient
temperature at the time of installation is irrelevant.
1. Ramming IPE160 posts
The minimum 2,500 mm long IPE160 post is to be driven vertically into the subgrade
with a suitable pile driver, so that the upper edge of the post section is 1,350 ±40
mm above the reference level. The three elongated holes 20x40 must be on the
upper end of the post section (post head) on the side facing the traffic.
The pile driver must be equipped with a suitable drive head to fit the IPE140 section,
in order to prevent deformation or damage to the hot-dip galvanised coating on the
post head. A guide adapted to the IPE140 section is to be mounted to the pile driver
near the upper edge of the ground in order to ensure precise positioning of the post
during the pile driving process.
The regulation centre distance of the posts is 1900 mm.
Figure 1