Manual VIPA CPU 21x
Chapter 6 Deployment of the CPU 21xDPM
HB103E - Rev. 05/45
6-13
Commissioning and Start-up behavior
•
Turn off your power supply
•
Build up your system
•
Cable your system
•
Plug in your MMC with CPU program and Profibus project
•
Turn on your power supply
•
For transferring your project from the MMC into the CPU, request an
OVERALL_RESET
Turn on the power supply. The course of events, described under "start-up
behavior", is following.
The following picture shows the approach once more:
3 Sec.
R
S
PW
SF
FC
MC
RN
ST
MR
3Sec.
RN
ST
MR
RN
ST
MR
RN
ST
MR
R
S
PW
SF
FC
MC
R
S
PW
SF
FC
MC
R
S
PW
SF
FC
MC
When the CPU is delivered it has been reset.
After a STOP
→
RUN transition the CPU switches to RUN without
program.
After NETZ_EIN (power on), the DP master tries to get parameters from
the CPU.
For the master doesn't get valid parameters from the CPU, it starts with
default parameters (Addr.:1, 1.5MBit) from its ROM and shows this via the
"IF"-LED.
Check list for
commissioning
Turn on
power supply
OVERALL_RESET
Default boot
procedure, as
delivered
Summary of Contents for CPU 21 Series
Page 1: ...Manual VIPA CPU 21x Order No VIPA HB103E Rev 05 45 ...
Page 2: ...Lerrzeichen ...
Page 6: ...About this Manual Manual VIPA CPU 21x Subject to change to cater for technical progress ...
Page 10: ...Contents Manual VIPA CPU 21x iv HB103E Rev 05 45 ...
Page 30: ...Chapter 1 Principles Manual VIPA CPU 21x 1 18 HB103E Rev 05 45 ...
Page 58: ...Chapter 2 Hardware description Manual VIPA CPU 21x 2 28 HB103E Rev 05 45 ...
Page 80: ...Chapter 3 Deployment CPU 21x Manual VIPA CPU 21x 3 22 HB103E Rev 05 45 ...
Page 178: ...Chapter 5 Deployment CPU 21x 2BT02 with H1 TCP IP Manual VIPA CPU 21x 5 48 HB103E Rev 05 45 ...