Vitodens 200-W B2HB 45, 57 Installation
5680 493 - 05
28
Boiler Connections
Connections
(continued)
Condensate connection
The Vitodens 200-W B2HB boiler comes with a built-
in condensate trap. An external trap is not required
when connecting the field drain to flexible discharge
tubing. Discharge tubing (field supplied) must be of 1 in.
diameter.
Use CPVC, PVC or other material approved by codes
listed below.
The drain pipe and fittings must conform to ANSI
standards and ASTM D1785 or D2846. CPVC or PVC
cement and primer must conform to ASTM D2564 or
F493. In Canada use CSA or ULC listed schedule 40
CPVC or PVC drain pipe, fittings and cement.
If the condensate outlet of the Vitodens 200-W B2HB
boiler is lower than the drain, a condensate pump must be
installed. Select a pump which is approved for condensing
boiler applications. To avoid condensate spillage, select
a pump with an overflow switch. The drain connection
must terminate into an open or vented drain as close to
the boiler as possible to prevent siphoning of the boiler
drain.
1. Install the condensate drain pipe with a suitable
gradient. Pull the condensate hose so far out of the
boiler that no unnecessary bends are created inside
the boiler. Check tightness of siphon connection.
IMPORTANT
Pipe ventilation must take place between the siphon trap
and the neutralization unit (if applicable).
IMPORTANT
As shipped, the flexible discharge tubing
E
will be found
to be pushed up inside the boiler housing. Ensure the
condensate drain pipe is pulled down and positioned to
allow the condensate to properly drain.
IMPORTANT
Do not connect the drain pipe from any other appliance,
such as water softener backwash pipe, to Vitodens
condensate drain pipe.
2. Discharge condensate from the boiler into the vented
drainage system, either directly or (if required) via a
neutralization unit (accessory).
Installation Instructions of Neutralization Unit
(if applicable)
Legend
A
Retaining clip
B
Siphon trap
C
Flexible discharge tubing
D
Flexible discharge tubing
Condensate Connection for Vitodens
200-W, models B2HB 45, 57
Condensate installation example:
Air gap
3. Ensure the condensate discharge tubing is vented
to the atmosphere prior to being plumbed into the
neutralization
unit.