[51]
98MANALIDP10AV Rev. A 3/23/11
To rotate the process covers, refer to Figure 7 and proceed as follows:
1. Remove the process covers from sensor by removing two hex head bolts.
2. Replace gaskets in process covers.
3. Rotate the process covers so that the longer tab is at the bottom.
4. Reinstall process covers and bolts. Torque cover bolts to 100 N m (75 lb ft) in several
even increments. Torque values are 66 N m (50 lb ft) when optional 316 ss bolts are
specified.
5. Pressure test the sensor and process cover assembly by applying a hydrostatic pressure
of 150% of the maximum static and overrange pressure (see page 2) to both sides of
the process cover/sensor assembly simultaneously through the process connections.
Hold pressure for one minute. There should be no leakage of the test fluid through
the gaskets. If leakage occurs, retighten the cover bolts per Step 4 or replace the gaskets
and retest.
!
CAUTION
Perform hydrostatic test with a liquid and follow proper hydrostatic test procedures.
Summary of Contents for IDP10-A
Page 14: ... 14 98MANALIDP10AV Rev A 8 16 11 ...
Page 16: ... 16 98MANALIDP10AV Rev A 8 16 11 ...
Page 26: ... 26 98MANALIDP10AV Rev A 8 16 11 ...
Page 35: ... 35 98MANALIDP10AV Rev A 8 16 11 ...
Page 37: ... 37 98MANALIDP10AV Rev A 8 16 11 IDP10 A and IDP10 V Calibration ...
Page 40: ... 40 98MANALIDP10AV Rev A 8 16 11 IDP10 A and IDP10 V Configuration ...