INSTALLING RECTIFIER MODULES
Refer to the rectifier instruction manual UM1R481000e3 for a rectifier installation procedure.
INITIALLY STARTING, CONFIGURING, AND CHECKING
SYSTEM OPERATION
Important Safety Instructions
CAUTION!
Performing various steps in the following procedures may cause a service interruption
and/or result in the extension of alarms. Notify any appropriate personnel before starting these
procedures. Also, notify personnel when these procedures are completed.
Initial Startup Preparation
•
Ensure that all blocks (except the last one) in the “Installation Acceptance Checklist” starting on page 11
have been checked.
•
Ensure that rectifier mounting positions are filled by a rectifier module or a blank module as required.
•
Refer to the separate Mini Control Unit User Manual (UM1M831ANA) supplied with your power system
for complete controller operating information.
•
Refer to the configuration drawing (C-drawing) supplied with your power system documentation for
factory settings of adjustable parameters.
Initially Starting the System
NOTE!
After power is initially applied to the system it takes several seconds for the rectifier modules to
begin producing power and the control module initialization routine takes several minutes.
Procedure
1.
Apply battery power to the system by closing the external battery disconnect(s) or protective device(s)
that supplies battery power to the system, if furnished. Close the system’s internal battery disconnect
circuit breakers, if furnished.
2.
Apply rectifier AC input power to the system by closing ALL external AC disconnects or protective
devices that supply rectifier AC input power to the rectifier mounting shelf.
3.
Rectifiers automatically start.
4.
The Mini Control Unit starts and goes through an initialization process. See “Mini Control Unit
(Controller) Initialization” on page 74.
5.
Place each distribution circuit breaker (if furnished) to the ON position.
6.
Refer to “Configuring the System” on page 74 and set the Mini Control Unit as required for your
application. Note: Your system may be pre-programmed for your application. Refer to the configuration
drawing (C-drawing) supplied with your power system documentation.
7.
Refer to “Checking System Operation” on page 79 and check system operation.
8.
Refer to “Checking System Status” on page 85 and check system status.