3
Connect one cable to one PDU strip.
4
Connect the other cable to the other PDU strip.
See “Turning on the hardware and verifying operation” on page 49.
Turning on the hardware and verifying operation
The appliance and the storage shelves must be turned on in a specified order. If
the hardware is not turned on correctly the appliance RAID controller may not
recognize some storage units.
49
Installation procedures
Turning on the hardware and verifying operation
Summary of Contents for NetBackup 5240
Page 4: ......
Page 22: ...Preinstallation requirements Prerequisites for IPMI configuration 22 ...
Page 42: ...Installation procedures Connecting a 4TB appliance to more than one storage shelf 42 ...
Page 43: ...43 Installation procedures Connecting a 4TB appliance to more than one storage shelf ...