Commissioning
14.02.11
BRI-7570_020
31
5.3. COMMISSIONING
When commissioning the machine, proceed as follows:
Make sure, that transport safeguard is removed.
1. Switch on the main switch at the switch cabinet (see page
34, Ill. 12, Pos. 3).
2. Press reset button (see page 34, Ill. 12, Pos. 2).
3. Open shut-off valve of the compressed-air
slowly
(see
page 29, Ill. 8, Pos. 1).
The heating plate opens.
4. If pressing machine is connected to a central suction, ad-
just suction valve (option, see chapter 5.3.1).
Summary of Contents for BRI-7570/101 FPD
Page 10: ...Scope of delivery 6 BRI 7570_020 14 02 11 ...
Page 18: ...Safety tests 14 BRI 7570_020 14 02 11 ...
Page 24: ...Disconnect procedures 20 BRI 7570_020 14 02 11 ...
Page 54: ...Maintenance and inspection table 50 BRI 7570_020 14 02 11 ...
Page 60: ...Emergency 56 BRI 7570_020 14 02 11 ...
Page 62: ...Dismantling Disposal 58 BRI 7570_020 14 02 11 ...
Page 67: ...EC declaration of conformity 14 02 11 BRI 7570_020 63 13 EC DECLARATION OF CONFORMITY ...
Page 68: ...EC declaration of conformity 64 BRI 7570_020 14 02 11 ...