Installation
Fuel Conditioner (FC) Installation
15
Installing FC Into Sump
1. The dimensions of the FC are shown in Figure
12 and will require a minimum of 37 inches of vertical clearance
(from manway to sump cover). This clearance must be confirmed when the HydrX site inspection is conducted
prior to ordering the equipment.
Figure 12. FC Dimensions
2. Check the lifting bolt on the top of the FC and make sure it is well tightened as it will support the approximate
145-pound weight of the assembly. Loosen the two supporting clamps on the FC, if necessary, so they are
open enough to clear the WID Riser.
3. Utilizing a tripod and winch connected to the FC eyebolt, carefully lower the FC down into the sump and onto
the Guide Tube riser until the two FC support clamps are below the Guide Tube flange and the assembly has
bottomed against the manway.
4. Orient the FC until the hose connections on the FC manifold are facing the center of the manway (see
2). If necessary due to space limitations, the FC can face the opposite way. Once the FC is in its final
position, tighten the two FC support clamps securely.