Operation Manual
-
6
-
Chap 4 Firstly testing when energized
4-1 Installation
Place the machine on a horizontal table, adjust the height of the machine pillars
to make it stable. Do keep enough room in front and behind of the machine. And
prevent from laying it in a place of quack, strong electromagnetic disturbance or
thick dirt-powder.
To ensure the machine work safely and reliably, please connect to the ground
effectively.
Plug the power cord in the power socket of the machine and a 220V/110V AC
power outlet, and turn on the switch, and the red light lights up. Now the carriage
can move to the right side and the roller rotates automatically, thus complete the
automatic reset. If it fails to reset, press the “RESET” key please.
At the same time of turning on the switch, cutter bracket will be raised about 1.5
to 2 mm. And pressing any direction key will make it fall down.
If all goes on as the above, that proves the machine operation properly.
4-2 Remote
The machine can be communicated with computer by serial port (COM1, 2, 3, 4)
or parallel port, but can’t use them at the same time.
Using parallel port can reduce communication time and improve the efficiency
of computer.
Remote steps:
A.
Turn off the computer and the machine.
B.
Connect the communication cable between the according interface of the
machine and of the computer.
C.
Turn on the computer and the machine, and wait for the machine
correctly resetting.
D.
Start cutting software or another after confirming the software setting
(interfaces, bode-rate and commands sets) matched to the machine.
Output graphical data to the machine, and it will begin to cut.