ULB PROPRIETARY RIGHTS NOTICE
- This document contains the confidential and proprietary information of ULB. You may not
possess, use, copy or disclose this document or any information in it for any purpose without express written permission. Neither receipt
from any source, nor possession of this document, constitutes such permission. Possession, use, copying or disclosure by anyone
without express written permission of ULB is not authorized and may result in criminal and/or civil liability.
C:\Users\Service-Eng\Desktop\Mx\Manuals\ULB-R110 MANUAL_rev02.docx Page
27
of
42
Physical connection
1) Each load bank has one input port (PORT-1, E2A) and one output port (PORT-2,
E3A) located just below display assembly on the load bank.
2) Master load bank will have no connection on the input port. Connect networking
cable (E610A) from output port of Master load bank to the input port of next load
bank (Slave-1). Similarly, connect networking cable from out port of Slave-1 load
bank to input port of Slave-2 Load bank. Connect Slave-3 and Slave-4 in similar
way.
3) Make sure network resistor (E544A), located on TB1 inside each load bank are
placed in line for Master and last slave in the network e.g Slave-4. However this
network resistor must be pulled out for any load bank between Master and last
slave e.g from Salve-1, Slave-2 and Slave-3
Powering up Master – Slave Load banks
Note: For master to identify all salves load banks, master load bank should be powered up
last (i.e power up all slave load banks first) or all load banks in the network should be
powered up simultaneously.
If steps of physical connection, settings and powered up are done correctly then following
screen should be displayed on Master load bank,(see figure-13)
Figure-13 Multiple load bank operation
Click <MULTIPLE> to operate load banks in Master – Slave mode. Following screen
showing ID, KW capacity, Fault and communication status of each load bank will show on
master load bank