AV30 PRE-INSTALLATION REQUIREMENTS | AV30 Pre-Installati on Requirements | v. 3.0
7 / 37
EQUIPMENT MANIFEST
Use this checklist as a manifest to ensure all equipment is delivered and on site.
Chiller
Your chiller will most likely be shipping directly from the manufacturer via LTL freight.
TruSteel will provide tracking when available.
Please check the delivered chiller for damage before receiving.
Chiller Model #:
Chiller Serial #:
☐
Chiller Arrived With No Damage
☐
Expansion Tank
☐
Remote Control
Water Heater
The heater unit will be delivered directly from the manufacturer. Please be aware that
the heater will take at least 2 weeks to be manufactured.
Tracking will be provided when available.
Heater Model #:
Heater Serial #:
☐
Electric Water Heater Arrived
Manifold Package
The manifold package will be shipped directly from TruSteel. It will
include: VFD [Variable Frequency Drives], Taco Recirculating Water Pump, Chiller Bypass
Manifold, Water Heater Manifold.
Note: If we determined are using your own chiller, or heater, we may not need to send
this package.
☐
Heater Manifold Pieces: Pressure Release/Gauge Section (Medium), Fill Port/Filter
Screen Section (Big)
☐
Expansion Tank (Blue Tank)