Coupled dampers (for plate heat exchanger)
Personnel:
HVAC technician
Protective equipment:
Industrial safety helmet
Protective clothing
Protective gloves
Safety shoes
1.
Check that the friction locking of the linkage is cor-
rect.
2.
Check the direction of rotation direction and
ensure that the blades fully open and close.
3.
Check that all screw joints and connections are
tight.
ð
The coupled multileaf dampers have been set
up.
6.3.7
Sound attenuator
Setting up sound attenuators
The splitter filling is made of non-combustible absorp-
tion material to DIN 4102.
Personnel:
HVAC technician
Protective equipment:
Industrial safety helmet
Protective clothing
Protective gloves
Safety shoes
Check splitters for damage and contamination.
ð
The sound attenuator has been set up.
6.3.8 Rotary heat exchanger
WARNING!
Risk of injury from rotating parts!
Incorrect handling, e.g. reaching into rotating parts,
can lead to serious injuries.
Never reach into or tamper with the storage mass
–
Switch off the system before you start working on
movable parts of the rotary heat exchanger and
secure it against accidentally being switched on
again. Wait until all parts have come to a stand-
still.
–
Do not put a damaged or defective rotary heat
exchanger into operation.
Adjusting the rotary heat exchanger
The storage mass of the rotary heat exchanger is fac-
tory set. You may have to adjust the storage mass to the
actual installation conditions, see
‘Adjusting the storage mass’ on page 71
.
Setting up the rotary heat exchanger
Personnel:
HVAC technician
Protective equipment:
Protective clothing
Hearing protection
Industrial safety helmet
Protective gloves
Safety shoes
Ensure that permitted values for parameters such as
temperatures or differential pressure are not
exceeded.
1.
Check whether the system has been correctly
installed.
2.
Inspect the rotary heat exchanger for foreign
matter.
3.
Check that the rotor moves freely.
See the manufacturer's documentation
Appendix A ‘Adjusting the storage mass’
4.
Check the rotation direction of the rotor and
change it on the motor controller, if necessary.
Follow the manufacturer's operating instructions.
If the heat exchanger includes a purge sector,
the rotating storage mass passes from the
extract air via the purge sector to the supply
air.
5.
Check that the control module functions correctly.
6.
Check the drive belt tension.
7.
Setting up the drive equipment,
.
Initial commissioning
Setting up and adjusting AHU casing units > Rotary heat exchanger
Air handling unit X-CUBE X2 / X-CUBE X2 compact
59