65
6. Operation and Configuration of S3M UPS Models
and Battery Cabinets
Step 5: Setting Aver Changing Duration (min)
Setting the Average Charging Duration in minutes is an estimation of the boost charger time duration to charge new batteries
to 90% capacity at 25°C. Obtain the recommended Average (Aver) Charging Duration (min) number based on the specific
S3M UPS and battery cabinet model combination from the chart in
Section 6.4
. Note the recommended battery boost charge
durations are estimates only based on new batteries. These numbers may change with the age of the batteries and the battery
ambient temperature. To change the
Aver Charging Duration
, press directly on the defaulted 240 value in the display.
• The Average (Aver) charging duration is the battery boost charge time limit. The value can be 1~999 min. The default is
value 240 (4 hours).
EOD Battery Volt:
End of discharge voltage is the low voltage cutoff of the batteries during a battery mode operation. The
value can be 1.60~1.90. The default value is 1.67V/cell, or 10.02Vdc per battery.
Float Temp Compen Coeff:
Modifies the voltage of compensation after enabling the switch. The value can be
0.001~0.007V/cell/°C. The default value is 0.003V/cell/°C.
Boost Charge Setting:
Boost charge can be set to Disable or Enable. The default value is Enable.
No Battery Warning:
Keep this alarm enabled if you want the UPS to provide a warning when no batteries are present. The
default value is Alarm.
Summary of Contents for BP240V09
Page 38: ...38 5 Installation Figure 5 32 Wiring Diagram for Installation of 80 Batteries ...
Page 46: ...46 5 Installation Figure 5 41C Front Layer 3 Layer 2 Layer 1 Rear ...
Page 49: ...49 5 Installation Figure 5 44A 2 Remove top right side and left side plates Figure 5 44 ...
Page 54: ...54 5 Installation 14 Reinstall the covers and the screws Figure 5 53 Figure 5 53 ...
Page 113: ...113 5 Instalación Figura 5 32 Diagrama de Cableado para la Instalación de 80 Baterías ...
Page 121: ...121 5 Instalación Figura 5 41C Front Layer 3 Layer 2 Layer 1 Rear ...
Page 129: ...129 5 Instalación 14 Reinstale las cubiertas y los tornillos Figura 5 53 Figura 5 53 ...
Page 196: ...196 5 Installation Figure 5 41C Front Layer 3 Layer 2 Layer 1 Rear ...
Page 204: ...204 5 Installation 14 Réinstaller les couvercles et les vis Figure 5 53 Figure 5 53 ...