RLC-ADF005D-EN
1
Optimus™ Model RTHD Chiller
Installation Completion Check Sheet and Request for Trane Service
Important:
A copy of this completed form must be submitted to the Trane service agency that will be responsible for the start-
up of the chiller. Start-up will NOT proceed unless applicable items listed in this form have been satisfactorily
completed.
See unit IOM RTHD-SVX01*-EN for detailed installation instructions.
To: Trane
Service
Office:
S.O. Number:
Serial Numbers:
Job/Project Name:
Address:
The following items are being installed and will be completed by:
Important:
Start-up must be performed by Trane or an agent of Trane specifically authorized to perform start-up of Trane
®
products. Contractor shall provide Trane (or an agent of Trane specifically authorized to perform start-up) with
notice of the scheduled start-up at least two weeks prior to the scheduled start-up.
Important:
It is required that heaters are energized for a minimum of 24 hours prior to start up. Therefore, chiller
should have power for this amount of time before Trane Service arrives to do start-up.
Check boxes if the task is complete or if the answer is “yes.”
1. Screw Chiller
Installation meets foundation requirements.
In place and piped.
Isolation pads installed.
2. Piping
Note:
See bulletin RLC-PRB015*-EN for piping installation considerations affecting sound.
Chilled water piping connected to:
Evaporator
Air handling units
Pumps
Flow switch or flow proving device installed (if not factory provided)
Strainer installed and cleaned
Condenser and heat recovery condenser (as applicable) piping connected to:
Condenser
Pumps
Flow switch or flow proving device installed (if not factory provided)
Cooling tower
Heating loop (as applicable)
Make-up water connected to cooling tower
Water supply connected to filling system
Does unit have freeze inhibitor? If unit has freeze inhibitor:
Verify type and concentration correct per unit submittal
Calculate and record freeze point of the solution: _____________________________
Systems filled
Pumps run, air bled from system
Strainer installed in entering water piping (evaporator and condenser) and cleaned
Relief valve ventilation piping installed (if applicable)
3. Flow balancing valves installed
Leaving chilled water
Leaving condenser water
Proper porting to measure flow and balance
Optional heat recovery or auxiliary condenser water (if applicable)
Summary of Contents for Optimus RTHD
Page 27: ...Installation Mechanical RTHD SVX01K EN 27...
Page 28: ...Installation Mechanical 28 RTHD SVX01K EN...
Page 29: ...Installation Mechanical RTHD SVX01K EN 29...
Page 54: ...Controls 54 RTHD SVX01K EN Figure 23 Tracer TU...
Page 88: ...Log and Check Sheets 88 RTHD SVX01K EN Page Left Intentionally Blank...
Page 95: ...Notes RTAF SVX001K EN 95...