background image

5

General Information

Unit Description

Before shipment, each unit is leak tested, dehydrated,
charged with refrigerant and compressor oil, and run tested
for proper control operation.

Each unit is equipped with manifolded scroll compressors.
Each manifolded set of compressors is piped in parallel and
utilizes a passive oil management system to maintain
proper compressor oil level.

The condenser coils are aluminum fin, mechanically bonded
to copper tubing. Copper-fin coils are optional. Louvered
condenser grilles for coil protection are standard.

Direct-drive, vertical discharge condenser fans are provided
with built-in thermal overload protection.

For “Ship with” items, refer to the Unit Component “Layout”
and “Ship with” Locations illustration.

If low ambient operation is required, low ambient dampers
are available as a field or factory installed option.

The evaporators used in each air-cooled cold generator are
of brazed plate construction. Each evaporator is fully insu-
lated. Entering and leaving temperatures of the chilled solu-
tion are measured by sensors located on the evaporator.

A liquid line solenoid valve, filter drier, sight glass, thermo-
static expansion valve, and service valves (liquid and dis-
charge) are provided on each circuit.

Standard controls for these units is a microelectronics con-
trol system that consists of a network of modules referred to
collectively as Unit Control Modules (UCM). The acronym
UCM is used extensively throughout this document when
referring to the control system network.

These modules, through Proportional/Integral control algo-
rithms, perform specific unit functions that governs unit op-
eration in response to chilled water temperature leaving the
evaporator. The stages of capacity control for these units is
achieved by starting and stopping the compressors.

The modules are mounted in the control panel and are fac-
tory wired to their respective internal components. They re-
ceive and interpret information from other unit modules,
sensors, remote panels, and customer binary contacts to
satisfy the applicable request for cooling. Refer to the fol-
lowing discussion for an explanation of each module func-
tion.

Human Interface Module (HI - Standard)
(1U65 = Local, 6U66 = Remote)

The Human Interface module enables the operator to adjust
the operating parameters for the unit using it’s 16 key key-
pad. The 2 line, 40 character LCD screen provides status
information for the various unit functions as well as menus
for the operator to set or modify the operating parameters.

Cold Generator Module (1U48) (CGM - Standard)

The Cold Generator Module (CGM) responds to cooling re-
quests by energizing the proper unit components based on
information received from other unit modules, sensors, re-
mote panels, and customer supplied binary inputs. It ini-
tiates unit operation based on that information.

Compressor Module (1U44) (MCM)

The Compressor module, upon receiving a request for me-
chanical cooling, energizes the appropriate compressors
and condenser fans. It monitors the compressor operation
through feedback information it receives from various pro-
tection devices. It also provides heat tape output control for
heat exchanger protection.

Interprocessor Communications Board (1U55) (IPCB -
Optional - used with Optional Remote Human Interface)

The Interprocessor Communication Board expands communi-
cations from the unit’s UCM network to a Remote Human Inter-
face Panel. DIP switch settings on the IPCB module for this ap-
plication should be; Switches 1 and 2 “Off”, Switch 3 “On”.

Trane Communications Interface Module (1U54) (TCI -
Optional - used with Trane ICS

TM

 

Systems)

The Trane Communication Interface module expands
communications from the unit’s UCM network to a Trane Tracer
100™ or a Tracer Summit™ system and allows external setpoint
adjustment and monitoring of status and diagnostics.

DIP Switch settings on the TCI module for these applica-
tions should be: Switches 1, 2, and 3 are “Off”

Generic Building Automation System Module
(1U51 = GBAS 0-5V, 1U98 = GBAS 0-10V)
Optional - used with Non-Trane Building Control System)

The Generic Building Automation System (GBAS) module
allows a non-Trane building control system to communicate
with the unit and accepts external setpoints in form of ana-
log inputs (0 - 5 DCV or 0 - 10 DCV depending on the mod-
ule selected) and a binary Input for demand limit. Five (5)
binary outputs are available on 0 - 5 DCV modules. One (1)
binary output and four (4) analog outputs are available on
the 0 - 10 DCV modules. Refer to the “Field Installed Con-
trol Wiring” section for the control wiring to the GBAS mod-
ule and the various desired setpoints with the correspond-
ing DC voltage inputs.

Lontalk Communication Interface Module (1U54)
(LCI Optional - used on units with Trane ICS

 or 3rd

party Building Automation Systems)

The LonTalk Communication Interface module expands com-
munications from the unit’s UCM network to a Trane Tracer
Summit

 or a 3rd party building automation system, that uti-

lizes LonTalk, and allows external setpoint and configuration
adjustment and monitoring of status and diagnostics.

Current Sensing Module (1U90) (CSM - Optional)

Current transformers located around two (2) of the main
power leads for each compressor monitors the running cur-
rent during compressor operation. The information is sent to
the CGM and can be accessed through the “Compressor
Status” submenu displayed at the Human Interface Module.

Superheat & Subcooling Module (1U91) (SSM -
Optional)

Monitors the system operating superheat and subcooling
through the use of pressure transducers, liquid line, and
suction line temperature sensors. The information is sent to
the SSM and can be accessed through the “Compressor
Status” submenu displayed at the Human Interface Module.

Input Devices & System Functions

The descriptions of the following basic Input Devices used
within the UCM network are to acquaint the operator with
their function as they interface with the various modules.
Refer to the unit’s electrical schematic for the specific mod-
ule connections.

Summary of Contents for IntelliPak CG-SVX02B-EN

Page 1: ...uct Section Refrigeration Product Hermetic Scroll Liquid Chillers Air Cooled Model CG Literature Type Installation Operation Maintenance Sequence 02B Date January 2005 File No SV RF CG SVX02B EN 105 S...

Page 2: ...ing the information within this manual and follow ing the instructions the risk of improper operation and or component damage will be minimized It is important that periodic maintenance be performed t...

Page 3: ...es 24 Final Water Piping Connections 26 Freeze Protection from Ambient Contitions 26 Field Installed Power Wiring 28 Disconnect Switch External Handle 28 Main Unit Power Wiring 28 Power Wire Sizing an...

Page 4: ...ary O P C20 20 Tons E 20 29 F w o Ice Machine L LonTalk Communication Interface Module C25 25 Tons 1 40 50 F w Ice Machine K Stock Unit C30 30 Tons 2 30 39 F w Ice Machine L LonTalk Communication Inte...

Page 5: ...iving a request for me chanical cooling energizes the appropriate compressors and condenser fans It monitors the compressor operation through feedback information it receives from various pro tection...

Page 6: ...the suction line s near the scroll compressor s The FPC are connected to the SCM or MCM Low Pressure Cutout LPC binary input in series with the LCC switch es The FPC switch is used to prevent the refr...

Page 7: ...additional 30 seconds after the stage change then Out put A will be de energized At this time only the fan un der the low ambient damper controlled by Output C will be on To prevent rapid fan cycling...

Page 8: ...eset diagnostic Evap Solution Flow Proving Switch will be generated Once this input is closed the diagnostic will clear and the compres sors will be allowed to resume operation If the flow switch fail...

Page 9: ...ncy Stop is a top priority command that will override all other commands received by the UCM A manual reset diagnostic will occur and an indication showing that the unit is shut down due to Emergency...

Page 10: ...10 General Information Module Mounting Locations Screw Hole...

Page 11: ...ery Notify the appropriate Trane office before installing or re pairing a damaged unit Unit Clearances Figure 1 illustrates the minimum operating and service clearances for either a single multiple or...

Page 12: ...12 Figure 1 Typical Installation Clearances for Single Multiple or Pit Applications...

Page 13: ...13 Figure 2 C20 Ton Unit Dimensional Data Recommended Clearances...

Page 14: ...14 Figure 2 C25 Ton Unit Dimensional Data Recommended Clearances...

Page 15: ...15 Figure 2 C30 Ton Unit Dimensional Data Recommended Clearances...

Page 16: ...16 Figure 2 C40 Ton Unit Dimensional Data Recommended Clearances...

Page 17: ...17 Figure 2 C50 Ton Unit Dimensional Data Recommended Clearances...

Page 18: ...18 Figure 2 C60 Ton Unit Dimensional Data Recommended Clearances...

Page 19: ...frigerant and oil charges Figure 3 Rigging and Center of Gravity Data WARNING Heavy Objects Do not use cables chains or slings except as shown Each of the cables chains or slings used to lift the unit...

Page 20: ...e holes in the isolator 6 Level the unit carefully Refer to the Leveling the Unit section 7 After the unit is level tighten the isolator base mounting bolts to secure them to the mounting surface Spri...

Page 21: ...DP 4 BLK RDP 3 GRN RDP 3 GRY RDP 3 RED RDP 3 GRN RDP 3 RED Cu RDP 4 BLK RDP 3 GRN RDP 3 GRY RDP 3 GRN RDP 3 GRY RDP 3 RED C40 Al RDP 3 GRY RDP 3 GRY RDP 3 GRY RDP 3 GRY RDP 3 GRN RDP 3 GRN Cu RDP 3 GR...

Page 22: ...28 CP 1 28 CP 1 31 CP 1 28 CP 1 28 CP 1 28 CP 1 28 CP 1 27 CP 1 28 CP 1 27 CP 1 28 C50 CP 1 31 CP 1 32 CP 1 31 CP 1 32 CP 1 31 CP 1 31 CP 1 31 CP 1 31 CP 1 28 CP 1 31 CP 1 28 CP 1 31 C60 CP 1 32 CP 2...

Page 23: ...ace by two ship ping braces that secure each compressor assembly rail to the unit s base rail To remove the shipping hardware follow the procedures below 1 Remove the four anchor bolts 2 front and 2 r...

Page 24: ...with over current protection to the main power terminal block 1TB1 or to an optional factory mounted nonfused disconnect switch 1S1 in the control panel Install and connect properly sized power supply...

Page 25: ...the filling pro cess Water Pressure Gauges Install pressure gauge s at the chiller barrel to monitor the entering and leaving solution pressure Note To prevent evaporator damage do not exceed 150 psi...

Page 26: ...26 Figure 7A Typical Water Access Holes for 20 through 60 Ton Units Figure 7B Edge Protector Installation Figure 7C Clearance Requirements Around Water Pipe...

Page 27: ...ainst ice formation at the lowest expected operating temperatures by adding a non freezing low temperature heat transfer fluid to the chilled water Ice making units with a termination setpoint of 27o...

Page 28: ...t both ends Be sure to install the ther mostat on the most exposed i e coldest portion of the pipe 4 Wrap the pipe with an insulation material and cover it with a weatherproof tape if additional prote...

Page 29: ...be closed with the handle in any one of the three positions outlined above provided it matches the disconnect switch position The handle can be locked in the OFF position While hold ing the handle in...

Page 30: ...30 Installation Figure 11 Typical Field Installed Power Wiring Refer to the Wiring Diagram Notes at the end of this Section Table 3 Customer Connection Wire Range...

Page 31: ...P OR MORE Calculation 1 MCA MOP and RDE MCA 1 25 x LOAD 1 LOAD 2 LOAD 4 MOP 2 25 x LOAD 1 LOAD 2 LOAD 4 Select a fuse rating equal to the MOP value If the MOP value does not equal a standard fuse size...

Page 32: ...223 250 4 35 5 55 5 251 376 6 4 1 0 9 CGAF 460 60 3 98 110 4 16 5 24 2 117 178 6 1 8 0 9 50 575 60 3 77 90 4 12 4 19 4 94 143 6 1 4 0 9 380 50 3 97 110 4 15 5 24 2 110 174 6 1 7 0 75 415 50 3 97 110 4...

Page 33: ...y output devices and the system components utilizing a DC analog input output signal to the unit Field Installed Control Wiring Before installing any connecting wiring refer to Figure 2 for the electr...

Page 34: ...t the Tracer 100 3 Connect the shielded twisted pair leads from the Tracer to the proper terminals on the UCM There is no polarity requirement for this connection 4 At the UCM the shield should be cut...

Page 35: ...35...

Page 36: ...36 Figure 12B Typical GBAS 0 5 Volt Connections Diagram...

Page 37: ...37...

Page 38: ...38...

Page 39: ...damage do not use untreated or improperly treated system water WARNING Live Electrical Components During installation testing servicing and troubleshoot ing of this product it may be necessary to wor...

Page 40: ...oper phasing of the electri cal supply to the unit is critical for proper operation and reli ability The compressor motor is internally connected for clockwise rotation with the incoming power supply...

Page 41: ...ELCI HGBP operation will be initi ated before the last compressor is turned Off Once HGBP has been initiated all subtract commands sent by the ELCI will be ignored If the Leaving Solution Temperature...

Page 42: ...compressor stages are locked On and the fractional part represents the duty cycle required for the next higher compressor stage For a 4 compressor unit the Load Value will range from 0 0 to 4 0 For a...

Page 43: ...culated reset amount is equal to selected Max Amount If Outside Air Temperature is between the Start Temp and the End Temp Max Amount calculated reset amount OA Start Temp Outside Air Temp OA Start Te...

Page 44: ...5 Start Temperature Range 66 81 Factory Preset 78 Zone Temperature Zone Reset Cooling Factory Preset 5 Table 8B Chilled Solution Reset Schedule based on Outside Air Temperature Active Leaving Solution...

Page 45: ...rcuit that has the most compressors operating The Lead Lag function is ignored treated as disabled when the Hot Gas Bypass option is installed and enabled When the UCM is powered up after a power loss...

Page 46: ...service test will begin after the TEST START key is pressed and the delay desig nated in this step has elapsed Press the ENTER key to confirm this choice WARNING Rotating Components During installati...

Page 47: ...47 System Start Up Figure 13 Evaporator Water Pressure Drop for CGAF C20 Through C60 Units English Note 1 Factor to convert Feet of Water to Lbs per Sq Inch PSI 2 3 Feet of Water 1 PSI...

Page 48: ...48 System Start Up Figure 14 Performance Adjustments and Solution Freezing Points Use Only When Leaving Brine Temperature is Between 40o F 50o F...

Page 49: ...ower including remote discon nects before servicing Follow proper lockout tagout procedures to ensure the power can not be inadvert ently energized Failure to disconnect power before ser vicing could...

Page 50: ...ressor 2A Off Compressor 2B Off Condenser Fans On Solution Pump On Note Pump operation is dependent upon proper solution flow proving switch operation Please see section titled Loss Of Flow Protection...

Page 51: ...key until the LCD displays the Start test in __Sec screen Press the key to designate the de lay before the test is to start This service test will begin after the TEST START key is pressed and the de...

Page 52: ...pressure at the suction line gauge access port located near the compressor b Using a Refrigerant Temperature chart convert the pressure reading to a corresponding saturated vapor temperature c Measur...

Page 53: ...ndition could damage com pressor bearings dur to reduced lubrication and could cause compressor mechanical failures When power has been Off for an extended period allow the crankcase heater to operate...

Page 54: ...n switch and Zone Temperature settings for comfort systems are correct Inspect the unit for misplaced tools hardware and de bris Turn the solution pump control circuit disconnect switch to the On posi...

Page 55: ...Compressor Replacement Table 12 lists the specific compressor electrical data and the circuit breaker operating ranges The compressor manifold system was purposely designed to provide proper oil retu...

Page 56: ...56 9 409 67 6 77 7 230 56 9 376 67 6 77 7 C30 2 15 380 415 25 2 174 29 5 33 9 460 25 1 178 29 5 33 9 575 19 9 143 23 6 27 2 200 39 4 269 43 2 49 7 230 39 4 251 43 2 49 7 C40 4 9 380 415 17 2 110 18 9...

Page 57: ...ese bearings add grease until a light bead appears all around the seal Do not over lubricate After greasing the bearings check the setscrews to en sure that the shaft is held securely to the bearings...

Page 58: ...erials Care must be taken to protect the roof from oil leaks or spills 5 Pour the cleaning solution into the sprayer If a high pres sure sprayer is used a do not allow sprayer pressure to exceed 600 p...

Page 59: ...end play or vibration and noise WARNING Rotating Components During installation testing servicing and troubleshoot ing of this product it may be necessary to measure the speed of rotating components H...

Page 60: ...t be obligated to pay for the cost of lost refrigerant No liability whatever shall at tach to the Company until said products have been paid for and then said liability shall be limited to the purchas...

Page 61: ...rol for Ice Building 40 Control for Process Applications 41 Current Sensing Module 5 D DC Conductors 33 See Table 6 discharge pressure approaches 405 7 psig 6 discharge pressure decreases to approxima...

Page 62: ...8 19 See Figure 3 S Saturated Condenser Temperature Sensors 6 saturated condensing temperature falls 6 scroll compressor design 53 Secure the isolator 19 shell and tube type evaporator 5 Shipwith item...

Page 63: ...63...

Page 64: ......

Reviews: