31
Installation
Power Wire Sizing and Protection Device Equations
To correctly size the main power wiring for the unit, use the appropriate calculation(s) listed below. Read the load definitions
that follow and use Calculation #1 for determining the MCA (Minimum Circuit Ampacity), MOP (Maximum Over current Pro-
tection), and RDE (Recommended Dual Element fuse size) for each unit. Use Calculation #2 to determine the DSS (Discon-
nect Switch Size) for each unit.
Load Definitions:
LOAD 1
= CURRENT OF THE LARGEST MOTOR (COMPRESSOR OR FAN MOTOR)
LOAD 2
= SUM OF THE CURRENTS OF ALL REMAINING MOTORS
LOAD 4
= CONTROL POWER TRANSFORMER
= AND ANY OTHER LOAD RATED AT 1 AMP OR MORE
Calculation #1
(MCA, MOP, and RDE)
MCA
= (1.25 x LOAD 1) + LOAD 2 + LOAD 4
MOP
= (2.25 x LOAD 1) + LOAD 2 + LOAD 4
Select a fuse rating equal to the MOP value. If the MOP value does not equal a standard fuse size as listed in NEC 240 - 6,
select the next lower standard fuse rating.
Note: If selected MOP is less than the MCA, then select the lowest standard maximum fuse size which is equal
to or larger than the MCA, provided the selected fuse size does not exceed 800 amps.
RDE
= (1.5 x LOAD 1) + LOAD 2 + LOAD 4
Select a fuse rating equal to the RDE value. If the RDE value does not equal a standard fuse size as listed in NEC 240 - 6
select the next higher standard fuse rating.
Note: If the selected RDE is greater than the selected MOP value, then select the RDE value to equal the MOP
value.
Calculation #2
Disconnect Switch Sizing (DSS)
DSS
= 1.15 X (LOAD 1 + LOAD 2 + LOAD 4)
Summary of Contents for IntelliPak CG-SVX02B-EN
Page 10: ...10 General Information Module Mounting Locations Screw Hole...
Page 12: ...12 Figure 1 Typical Installation Clearances for Single Multiple or Pit Applications...
Page 13: ...13 Figure 2 C20 Ton Unit Dimensional Data Recommended Clearances...
Page 14: ...14 Figure 2 C25 Ton Unit Dimensional Data Recommended Clearances...
Page 15: ...15 Figure 2 C30 Ton Unit Dimensional Data Recommended Clearances...
Page 16: ...16 Figure 2 C40 Ton Unit Dimensional Data Recommended Clearances...
Page 17: ...17 Figure 2 C50 Ton Unit Dimensional Data Recommended Clearances...
Page 18: ...18 Figure 2 C60 Ton Unit Dimensional Data Recommended Clearances...
Page 35: ...35...
Page 36: ...36 Figure 12B Typical GBAS 0 5 Volt Connections Diagram...
Page 37: ...37...
Page 38: ...38...
Page 63: ...63...
Page 64: ......